Question

The King Co. makes product AKUA10 and SKUB10 and is preparing an aggregate plan for the...

The King Co. makes product AKUA10 and SKUB10 and is preparing an aggregate plan for the next two quarters. SKUA10 takes one labor hour per unit to produce while SKUB takes two labor hours per unit to produce. At the beginning of Quarter 1 (Q1) there are 150 units of SKUA10 and 40 units of SKUB10 in inventory. There is no need for any ending inventory at the end of Quarter 2 (Q2). The sales for SKUA10 are forecasted to be 140 units in Q1 and 50 units in Q2, while the sales for SKUB10 are forecasted to be 55 units in Q1 and 45 units in Q2.

i) Identify an appropriated aggregate unit to assist in aggregate planning?

ii) What is the initial inventory in aggregate units?

iii) What is the aggregate sales forecast for each quarter?

iv) If a chase plan is used how much, in terms of aggregate units, will be produced in each quarter? According to this aggregate plan what will be inventory and backorders at the end of Q1 and at the end of Q2?

v) If a level plan is used how much, in terms of aggregate units, will be produced in each quarter? According to this aggregate plan what will be the inventory and backorders at the end of Q1 and at the end of Q2?

vi) Which aggregate plan has higher backorders?

vii)Which aggregate plan has higher ending inventory?

viii) Distribute the aggregate production plans determined in d) and e) to the two individual products for each of Q1 and Q2. Under your proposal what will be the inventory and backorders (in aggregate units) at the end of Q1?

Homework Answers

Answer #1
Sales Forecast
Q1 Q2 Beginning Inventory Ending Inventory Labour Hours
A 140 50 A 150 0 1
B 55 45 B 40 0 2
i) Identify an appropriated aggregate unit to assist in aggregate planning?
The appropriate aggregate unit used should be Labour Hours.
This is because units needed is directly correlated with it & this will enable us in getting correct boundary conditions.
ii) What is the initial inventory in aggregate units?
Initial inventory
A 150 (150*1)
B 80 (40*2)
Therefore, initial inventory equals 230 Labour Hours.
iii) What is the aggregate sales forecast for each quarter?
Quarter 1: 140 units of A & 55 units of B which equal 140*1+55*2= 250 Labour Hours
Quarter 2: 50 units of A & 45 units of B which equal 50*1+45*2= 140 Labour Hours
iv) If a chase plan is used how much, in terms of aggregate units, will be produced in each quarter?
According to this aggregate plan what will be inventory and backorders at the end of Q1 and at the end of Q2?
Chase Plan refers to completing the stipulated demand in the same quarter.
Quarter 1;-
A has a demand of 140 units while B has demand of 55 units
The supply needed= Demand - Opening Inventory for both A & B individually.
A=   140-150    =     -10 (Opening inventory of 10 units in Quarter 2)
B =      55-40   = 15
Quarter 1:- Total production will be 15*2 = 30 Labour Hours
Inventory at end of Quarter 1: 10 units of A= 10*1= 10 Labour Hours
No Backorders
Quarter 2:
A has a demand of 55 units while B has demand of 45 units
A = 55-10   =45
B = 45-0     = 45
Quarter 2: Total production will be 45*1+45*2 = 135 Labour Hours
Inventory at end of Quarter 2: 0 units
No Backorders
v) If a level plan is used how much, in terms of aggregate units, will be produced in each quarter?
According to this aggregate plan what will be the inventory and backorders at the end of Q1 and at the end of Q2?
Total demand of A: 190
Total demand of B: 100
Total production hours needed: 190*1+100*2 = 390 Labour Hours
Beginning inventory = 230 Labour Hours
Labour Hours needed/ Quarter: (390-230)/2= 70 Labour Hours
This equals aggregate units to produce each quarter .
Inventory at end of Q1: 230+70-(140*1+55*2)=50 Labour Hours. Backorders at end of Q1 = 0
Inventory at end of Q2: 50+70-(50*1+45*2)= -20 Labour Hours. Backorders at end of Q2 = 20 Labour Hours
vi) Which aggregate plan has higher backorders?
Level Plan has higher backorders
vii)Which aggregate plan has higher ending inventory?
Level Plan has higher ending inventory
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, subcontracting and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity and subcontracting capacity are 20 units per month each. Overtime cost is $30 per unit, subcontracting cost is 40 per unit, and backorder cost is $20 per unit, inventory holding cost is $5...
Planners for a firm are about to prepare the aggregate plan for one particular product that...
Planners for a firm are about to prepare the aggregate plan for one particular product that will cover the next six periods. Demand over those six periods is expected to be: 250, 200, 400, 500, 550, and 300 for total demand of 2,200. They have regular time capacity of 350 units per period and they plan to produce that many each period. They have unlimited overtime capacity. They wil only produce in overtime to prevent a backorder/backlog. They realize that...
17).ABP Co. reported the following per unit amounts in the current fiscal year: $75 sales price;...
17).ABP Co. reported the following per unit amounts in the current fiscal year: $75 sales price; $12.50 variable selling expense; $8.75 direct material; $14.50 direct labor; $16.25 manufacturing overhead. They also reported $26,250 in fixed selling expenses. How much is cost of goods sold? a).$75.00 b).$52.00 c).$39.50 d).$127.00 18).The sales budget reported the following sales in units for fiscal year 5. The company wants to maintain a desired ending finished goods inventory in the current quarter equal to 20% of...
You would like to construct an aggregate production plan for product CT34 for the four quarters...
You would like to construct an aggregate production plan for product CT34 for the four quarters of next year. Cost of regular production = 70 $/u Cost of overtime production = 95 $/u Inventory holding cost = 7 $/u/qtr Cost of increasing production = 80 $/u Cost of decreasing production = 110 $/u The regular production for the last quarter of this year = 1900 u Inventory level at the end of the last quarter of this year = 140...
Preparing a Production Budget Patrick Inc. makes industrial solvents. In the first 4 months of the...
Preparing a Production Budget Patrick Inc. makes industrial solvents. In the first 4 months of the coming year, Patrick expects the following unit sales: January 41,000 February 38,000 March 50,000 April 51,000 Patrick's policy is to have 21% of next month's sales in ending inventory. On January 1, it is expected that there will be 4,350 drums of solvent on hand. Required: Prepare a production budget for the first quarter of the year. Show the number of drums that should...
Preparing a Production Budget Patrick Inc. makes industrial solvents. In the first 4 months of the...
Preparing a Production Budget Patrick Inc. makes industrial solvents. In the first 4 months of the coming year, Patrick expects the following unit sales: January 41,000 February 38,000 March 50,000 April 51,000 Patrick's policy is to have 21% of next month's sales in ending inventory. On January 1, it is expected that there will be 4,400 drums of solvent on hand. Required: Prepare a production budget for the first quarter of the year. Show the number of drums that should...
What is aggregate planning? In the sample aggregate planning problem, change "for fudge for the next...
What is aggregate planning? In the sample aggregate planning problem, change "for fudge for the next four months is 120, 150, 100, and 70 pounds," to "130, 150, 110, and 60 pounds." Carry out the rest of the solution, with changed numbers, making sure, you follow the procedure used for "Level Strategy." The forecasted demand for fudge for the next four months is 120, 150, 100, and 70 pounds. a.     What is the recommended production rate if a level strategy...
Clarks Italian Ice is creating a sales budget for 2019. For the year, they expect to...
Clarks Italian Ice is creating a sales budget for 2019. For the year, they expect to sell 100,000 cases of popsicles at a price of $20 per case for total budget sales of $2,000,000. For each quarter the budget unit sales are Q1-10,000 ; Q2-30,000; Q3-40,000 ; Q4-20,000. Of the total sales, Clarks Italian Ice expects to collect 70% in the current quarter and the remaining 30% in the following quarter. Desired Units of finished goods inventory is 20% of...
Problem 9-4 Karam Inc. has compiled the following data in order to put together their first...
Problem 9-4 Karam Inc. has compiled the following data in order to put together their first quarter operating budget for 2011: January February March April Sales (units) 35,000 31,000 38,000 29,000 Each unit requires three hours of direct labor. Additional information: Karam sells each unit for $95. Company policy is to have 30 percent of next month's sales (in units) in ending finished goods inventory. Company policy is to have 40 percent of next month's production needs in ending raw...
Note: The company desires a minimum ending cash balance each month on $35,000. The beard grooming...
Note: The company desires a minimum ending cash balance each month on $35,000. The beard grooming products are sold to retailers for $20 each and the sales have been stagnant due to the Covid-19. However, the marketing department has been positive toward the end of the year due to season change and upcoming holiday. The marketing department has just sent you their forecasted quarter sales and marketing budget. Quarter 2020 Q4 2021 Q1 2021 Q2 2021 Q3 2021 Q4 2022...