Question

What is the optimum job sequence for the jobs listed below using Johnson's Rule? Processing time(hrs)...

What is the optimum job sequence for the jobs listed below using Johnson's Rule?

Processing time(hrs)

Job

Center 1

Center 2

d

13

23

e 23 14
f 16 18
g 20 17

A. e-g-f-d

B. d-g-f-e

C. d-f-g-e

D. e-d-f-g

E. f-e-d-g

Homework Answers

Answer #1

What is the optimum job sequence for the jobs listed below using Johnson's Rule?

  1. The smallest time is located in Job E (14 hours). Since the time is in Work Center 2, schedule this job last.

    Eliminate Job from further consideration.

    ? ? ? E
  2. The next smallest time is located in Job D (13 hours). Since the time is in Work Center 1, schedule this job first.

    Eliminate Job D from further consideration.

    D ? ? E
  3. The next smallest time after that is located in Job G (17 hours). Since the time is in Work Center 2, schedule this job last.

    Eliminate Job G from further consideration.

    D ? G E
  4. The only job left to consider is Job F.
    D F G E

Answer = (C) d-f-g-e

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at...
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, a. what is the job processing sequence? b. how much idle time does work center Beta have? Job Alpha Beta R 20 10 S 25 35 T 50 20 U 15 35 V 55 75
RESTORE machine shop makes customized replacement parts for older equipment. All customer jobs listed must be...
RESTORE machine shop makes customized replacement parts for older equipment. All customer jobs listed must be machined first, then polished. Determine the optimal processing sequence of the six jobs listed below. Jobs Machining Hrs Polishing Hrs A 5 4 B 7 3 C 3 2 D 4 1 E 1 2 F 3 4 job A is finished at time 21 11 9 13
You have been asked to sequence the following jobs. Task A must always be done before...
You have been asked to sequence the following jobs. Task A must always be done before Task B. Using Johnson's Rule, in what order will you do the jobs? Job Task A Task B A 3 6 B 7 6 C 5 2 D 5 8 E 4 7 F 9 3 G 1 4
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
If the following jobs are sequenced according to the SLACK rule then job A would be...
If the following jobs are sequenced according to the SLACK rule then job A would be completed on day (assume zero for today's date) Job - Processing Time (days) - Due Date A 8 12 B 6 15 C 11 17 D 7 10 E 3 8 Select one: A. 7. B. 15. C. 8. D. 12.
The scheduling rule that minimizes the makespan time for a set of jobs that must be...
The scheduling rule that minimizes the makespan time for a set of jobs that must be processed through a two-step system where every job follows the same sequence through the two processes is A. the shortest processing time (SPT). B. Johnson’s Rule. C. the assignment method. D. the minimal slack rule.
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
A random sample of marks scored by 20 students in a CAT is listed below. Calculate...
A random sample of marks scored by 20 students in a CAT is listed below. Calculate the sample mean and standard deviation: 29, 26, 13, 23, 23, 25, 17, 22, 17, 19, 12, 26, 30, 30, 18, 14, 12, 26, 17, 18 Select one: a. 20.50, 5.94 b. 20.50, 5.79 c. 20.85, 5.94 d. 20.85, 5.79
For the integral below, write a program to do the trapezoid rule using the sequence of...
For the integral below, write a program to do the trapezoid rule using the sequence of mesh sizes h = (b – a)/2, (b – a)/4, (b – a)/8, ..., (b – a)/128, where b – a is the length of the given interval: f(x) = e−x sin(4x), [0, pi], I(f) = (4/17)(1 − e^-pi) = 0.2251261368. Verify that the expected rate of error decrease is obtained. Attach your code and a plot of error vs. h.
Part A. In the past it has been found that the arrival time have a population...
Part A. In the past it has been found that the arrival time have a population mean value of μ = 13 and a population standard deviation of σ = 6.26. Using the given data, test whether this mean has changed. Use the critical value approach to test the hypothesis. The significance level alpha is set at 0.05 . The original data of time taken is given below. Show the process by using excel (Formulas). Part B. Test the hypothesis...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT