Question

Work with your group to practice the critical path method of scheduling Draw the network diagram...

Work with your group to practice the critical path method of scheduling

Draw the network diagram using the SmartArt tool in any Microsoft Office application

Follow the convention for drawing each node, allowing space for ES, EF, LS, LF and float

Identify all the paths in the schedule

Use the enumeration method to identify the critical path

Make a forward pass to find the early schedule dates

Make a backward pass to find the late schedule dates

Define the float for all activities

Activity Predecessor Duration
A none 5
B A 8
C B 2
D A 17
E B 6
F C, D, E 10
G F 4

Homework Answers

Answer #1

The critical path is thus A-D-F-G since the floats of each of these activities are zero. Total time of project completion = EF of 'G' = LF of 'G' = 36

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information is known about a project: a. Draw a network diagram b. Calculate the...
The following information is known about a project: a. Draw a network diagram b. Calculate the ES, EF, LS, LF and slack time and find the critical path for this project Activity Activity Time (days) Immediate Predecessor A 12 B 9 C 10 A D 10 A,B E 24 B F 10 A G 35 C H 40 D I 15 A J 4 E,G,H K 6 F,I,J
In the following table task durations are given in weeks. Use the three point to find:...
In the following table task durations are given in weeks. Use the three point to find: Activity Predecessor Optimistic Normal Pessimistic A None 2 4 6 B None 3 5 9 C A 4 5 7 D A 4 6 10 E B,C 4 5 7 F D 3 4 8 G E 3 5 8 Construct the (AON) Activity on Node network diagram Find each activity’s ES, EF, LS and LS Identify all paths. Which path is the critical...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
Please do it by type not pics. You're at home, before you start your internship, your...
Please do it by type not pics. You're at home, before you start your internship, your local city council heard you have experience in project management. They want to create a botanical garden in your city park and have asked you to create a PERT chart of the following tasks from their Work Breakdown Structure. Code Activity Time (in hours) Immediate Predecessor(s) A Planning 20 None B Purchasing 60 Planning C Excavation 100 Planning D Sawing 30 Purchasing E Placement...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
You're at home after the Spring Semester and before you start your internship, your local city...
You're at home after the Spring Semester and before you start your internship, your local city council heard you have experience in project management. They want to create a botanical garden in your city park and have asked you to create a PERT chart of the following tasks from their Work Breakdown Structure. Code Activity Time (in hours) Immediate Predecessor(s) A Planning 20 none B Purchasing 60 planning C Excavation 100 planning D Sawing 30 purchasing E Placement 20 sawing,...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...