Question

Given the following data, develop MRP tables and indicate the Planned order releases for all items....

Given the following data, develop MRP tables and indicate the Planned order releases for all items.

A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.)

Period

6

7

8

GR-A

0

100

900

On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for A and a lot size of 500 or multiples of 500 for C, F and G.

Draw the Bill of Material                  Fill up the Low level code Table

Item

Low level code

A

C

F

G

A

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

C

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

F

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

G

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time work force is fixed and it does not depend on the amount produced and hence may be omitted in the cost calculations. Overtime production costs an additional $1.00 per unit. Holding cost per unit per month is $2.00, and shortage cost is $5.00 per unit per month, (short units must be supplied at a later period, but within the 5 month planning horizon.) what is the total inventory holding cost (use ending inventory to calculate this cost), total shortage cost, total overtime cost and the total cost of your plan?

September

October

November

December

January

Demand

8000

12000

4000

11000

13000

Any unfulfilled order (from previous month/s)

Beginning Inventory

Production Units (Reg Time)

Production units (Overtime)

Quantity Available for shipment

Actual Shipment

Shortage

Ending Inventory

Target is 2000

Shortage cost

Inventory holding cost

Over time cost

Given the following data, develop MRP tables and indicate the Planned order releases for all items.

A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.)

Period

6

7

8

GR-A

0

100

900

On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for A and a lot size of 500 or multiples of 500 for C, F and G.

Draw the Bill of Material                  Fill up the Low level code Table

Item

Low level code

A

C

F

G

A

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

C

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

F

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

G

1

2

3

4

5

6

7

8

GR

EI

NR

PO Receipt

PO Release

Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time work force is fixed and it does not depend on the amount produced and hence may be omitted in the cost calculations. Overtime production costs an additional $1.00 per unit. Holding cost per unit per month is $2.00, and shortage cost is $5.00 per unit per month, (short units must be supplied at a later period, but within the 5 month planning horizon.) what is the total inventory holding cost (use ending inventory to calculate this cost), total shortage cost, total overtime cost and the total cost of your plan?

September

October

November

December

January

Demand

8000

12000

4000

11000

13000

Any unfulfilled order (from previous month/s)

Beginning Inventory

Production Units (Reg Time)

Production units (Overtime)

Quantity Available for shipment

Actual Shipment

Shortage

Ending Inventory

Target is 2000

Shortage cost

Inventory holding cost

Over time cost

Total cost of the Plan:

Total cost of the Plan:

Homework Answers

Answer #1

Product Structure Tree is following

Low level code table is following

Item Low level code
A 0
C 2
F 1
G 1

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 0 100 900 On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other...
Given the following data, develop MRP tables and indicate the Planned order releases for all items....
Given the following data, develop MRP tables and indicate the Planned order releases for all items. A is an MPS item. A needs 2 C's and 3 F’s. F needs 3 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.) Period 6 7 8 GR-A 400 0 300 On hand inventory for all items is 200 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, subcontracting and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity and subcontracting capacity are 20 units per month each. Overtime cost is $30 per unit, subcontracting cost is 40 per unit, and backorder cost is $20 per unit, inventory holding cost is $5...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7...
Consider the following requirements for a certain product. Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0 400 0 400 Beginning inventory = 500 units Setup cost = $500 per setup Lead time = 1 week Holding cost = $3 per unit per week a. Develop the lot-for-lot MRP table. b. Calculate the total relevant costs. Answer: Period 1 2 3 4 5 6 7 8 Gross requirements 0 200 200 500 0...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small company produces a variety of recreational and leisure vehicles. The sales & marketing manager has developed the following aggregate forecasts: Month Mar Apr May Jun Jul Aug Sep Forecast 50 44 55 80 70 40 50 Use the following information: Regular labor cost                  $240 per unit Overtime labor cost                $360 per unit Subcontracting cost                $400 per unit Regular capacity                     50 units per month Overtime...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order...
Calculate the cost of operating under the different MRP lot sizing techniques: Lot-for-Lot (L4L) Economic Order Quantity (EOQ) Least Total Cost (LTC) Least Unit Cost (LUC) Compare your results and state which method is the most cost efficient in this situation. Consider the following MRP lot sizing problem: Cost per item $50 Order/setup cost $75 Inventory carrying cost per item per week $1 Weekly net requirements: 1 2 3 4 5 6 7 8 75 90 100 90 80 95...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead...
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup cost is $9. There is a carrying cost of $0.02 per unit per week. Beginning inventory is 75 units. WEEK 1 2 3 4 5 6 7 8 9 10 Gross requirements 20 10 15 45 10 30 90 20 45 160 Use the least total cost lot-sizing method to determine the quantity to order with...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you have 30 workers. It is not possible to hire any additional workers until next Summer, at which time temporary workers will be hired at the beginning of Summer and laid off at the end of Summer. Therefore, no hiring or laying...