Given the following data, develop MRP tables and indicate the Planned order releases for all items.
A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.)
Period |
6 |
7 |
8 |
GR-A |
0 |
100 |
900 |
On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for A and a lot size of 500 or multiples of 500 for C, F and G.
Draw the Bill of Material Fill up the Low level code Table
Item |
Low level code |
A |
|
C |
|
F |
|
G |
A |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
C |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
F |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
G |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time work force is fixed and it does not depend on the amount produced and hence may be omitted in the cost calculations. Overtime production costs an additional $1.00 per unit. Holding cost per unit per month is $2.00, and shortage cost is $5.00 per unit per month, (short units must be supplied at a later period, but within the 5 month planning horizon.) what is the total inventory holding cost (use ending inventory to calculate this cost), total shortage cost, total overtime cost and the total cost of your plan?
September |
October |
November |
December |
January |
|
Demand |
8000 |
12000 |
4000 |
11000 |
13000 |
Any unfulfilled order (from previous month/s) |
|||||
Beginning Inventory |
|||||
Production Units (Reg Time) |
|||||
Production units (Overtime) |
|||||
Quantity Available for shipment |
|||||
Actual Shipment |
|||||
Shortage |
|||||
Ending Inventory |
Target is 2000 |
||||
Shortage cost |
|||||
Inventory holding cost |
|||||
Over time cost |
Given the following data, develop MRP tables and indicate the Planned order releases for all items.
A is an MPS item. A needs 4 C's, 2 F’s and 5 G’s. F needs 4 C’s and G needs 2 C’s. (I eliminated scheduled receipts since the problem did not have scheduled receipts.)
Period |
6 |
7 |
8 |
GR-A |
0 |
100 |
900 |
On hand inventory for all items is 300 and lead time for A is 1 period, and LT for all other items is 2 periods. Use lot-for-lot for A and a lot size of 500 or multiples of 500 for C, F and G.
Draw the Bill of Material Fill up the Low level code Table
Item |
Low level code |
A |
|
C |
|
F |
|
G |
A |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
C |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
F |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
G |
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
GR |
||||||||
EI |
||||||||
NR |
||||||||
PO Receipt |
||||||||
PO Release |
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time work force is fixed and it does not depend on the amount produced and hence may be omitted in the cost calculations. Overtime production costs an additional $1.00 per unit. Holding cost per unit per month is $2.00, and shortage cost is $5.00 per unit per month, (short units must be supplied at a later period, but within the 5 month planning horizon.) what is the total inventory holding cost (use ending inventory to calculate this cost), total shortage cost, total overtime cost and the total cost of your plan?
September |
October |
November |
December |
January |
|
Demand |
8000 |
12000 |
4000 |
11000 |
13000 |
Any unfulfilled order (from previous month/s) |
|||||
Beginning Inventory |
|||||
Production Units (Reg Time) |
|||||
Production units (Overtime) |
|||||
Quantity Available for shipment |
|||||
Actual Shipment |
|||||
Shortage |
|||||
Ending Inventory |
Target is 2000 |
||||
Shortage cost |
|||||
Inventory holding cost |
|||||
Over time cost |
Total cost of the Plan:
Total cost of the Plan:
Product Structure Tree is following
Low level code table is following
Item | Low level code |
A | 0 |
C | 2 |
F | 1 |
G | 1 |
Get Answers For Free
Most questions answered within 1 hours.