You're at home
after the Spring Semester and before you start your internship,
your local city council heard you have experience in project
management. They
want to create a botanical
garden in your city park and have asked you to create a PERT chart
of the following tasks from their Work Breakdown Structure.
Code
Activity
Time (in hours)
Immediate Predecessor(s)
A
Planning
20
none
B
Purchasing
60
planning
C
Excavation
100
planning
D
Sawing
30
purchasing
E
Placement
20
sawing, excavation
F
Assembly
10
placement
G
Infill
20
assembly
H
Outfill
10
assembly
I
Decoratoin
30
infill, outfill
a. Using Activity-on-Node,
create a precedence diagram of the garden project (6 points)
b. using ES, EF, LS, LF,
determine the critical path of this project. (6 points)
c. How long will this project
take (in hours)?
(4 points)
d. One of the city planners
insists that if they can reduce purchasing by 20 hours, the project
will be done sooner. Is he correct? Why or why
not?