MRP IN MANUFACTURING 1. Each E subassembly is made up of 6 G parts, 20 H parts, and ONE J part. Draw the product structure tree diagram. Using the product structure tree diagram and the information provided below, Completeth e following MRP Report Transaction processing for PART E and PART G ONLY if the following information is provided: ( Do not order more quantity of any resources that are needed to maintain the production)
E subassembly | G part | H part | J part | ||
Order Lot size | 200 | 250 | 1000 | 1200 | |
Lead time | 0wk | 1wk | 2wks | 2wks | |
On hand | 200 | 300 | 700 | 700 | |
Safety Stock | 100 | 50 | 150 | 400 | |
Scheduled Receipt | 1000, 200 | 500, 900 | 600 | 500 |
Part E | 1 | 2 | 3 | 4 | 5 | 6 |
Gross Required | 1500 | 1200 | 800 | 1000 | 900 | 600 |
Scheduled Receipt | 1000 | 200 | ||||
Available | ||||||
Net Requirement | ||||||
Planned Order Receipt | ||||||
Planned Order Released |
Part G | 1 | 2 | 3 | 4 | 5 | 6 |
Gross Required | ||||||
Scheduled Receipt | 500 | 900 | ||||
Available | ||||||
Net Required | ||||||
Planned Order Receipt | ||||||
Planned Order Release |
We can solve this question in excel using following formula:
This will give our final solution as :