Question

JDI, Inc. is trying to decide whether to make or buy a part (#J-45FPT). Purchasing the...

JDI, Inc. is trying to decide whether to make or buy a part (#J-45FPT). Purchasing the part would cost $1.50 each. If they design and produce it themselves, it will result in a per unit cost of $1.00. However, the design investment would be $50,000. Further, they realize that for this type of part, there is a 25% chance that the part will need to be redesigned at an additional cost of $50,000. Regardless of whether they make or buy the part, JDI will need 150,000 of these parts. Using decision trees analysis and EMV, what should JDI do? Show the decision tree.

Homework Answers

Answer #1

Decision Tree:

For Purchase, cost = 150000*1.5 = 2,25,000

For Design and Produce:

Cost = 0.75*(1*1,50,000) + 0.25*(1*1,50,000 + 50,000) = 1,62,500

Also, there is 50,000 cost for initial design

Total cost = 1,62,500 + 50,000 = 2,12,500

Hence, the best option is to Design and Produce themeselves as overall cost is low

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A manager is trying to decide whether to buy one machine or two. If only one...
A manager is trying to decide whether to buy one machine or two. If only one is purchased and demand proves to be excessive, the second machine - can be pur­chased later. Some sales will be lost, however, because the lead time for producing this type of machine is 6 months. In addition, the cost per machine will be lower if both are purchased at the same time. The probability of low demand is estimated to be 0.20. The after-tax...
The government has been trying to decide whether or not to purchase any stealth bombers. One...
The government has been trying to decide whether or not to purchase any stealth bombers. One of the arguments in favor of purchasing the bombers is that since so much money has been spent on their development, it would be a waste of money not to buy any. What is the major problem with this argument? a. It doesn't consider the opportunity cost of the money that has been spent. b. It includes sunk costs in the decision. c. It...
Ronald Lau, chief engineer at South Dakota Electronics, has to decide whether to build a new...
Ronald Lau, chief engineer at South Dakota Electronics, has to decide whether to build a new state-of-the-art processing facility. If the new facility works, the company could realize a profit of $200,000. If it fails, South Dakota Electronics could lose $180,000. At this time, Lau estimates a 60% chance that the new process will fail. The other option is to build a pilot plant and then decide whether to build a complete facility. The pilot plant would cost $10,000 to...
Lavender is considering whether to make or buy some of the components used in the production...
Lavender is considering whether to make or buy some of the components used in the production of deodorants. The annual cost of producing these components used by the company is as follows: Component A Component B Direct variable manufacturing costs $300,000 $200,000 Direct fixed manufacturing costs $100,000 $50,000 Allocated overhead $50,000 $50,000 Quantity produced 100,000 200,000 The fixed manufacturing costs allocated to component A would be reduced by 80% if the company were to discontinue production of component A. As...
A grapefruit farmer in central Florida is trying to decide whether to take protective action to...
A grapefruit farmer in central Florida is trying to decide whether to take protective action to limit damage to his crop in the event that the overnight temperature falls to a level well below freezing. He is concerned that if the temperature falls sufficiently low and he fails to make an effort to protect his grapefruit? trees, he runs the risk of losing his entire? crop, which is worth approximately? $75,000. Based on the latest forecast issued by the National...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2022. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were: direct...
The management of Marigold Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Marigold Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 7,900 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Shatner Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,000 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...
The management of Bramble Manufacturing Company is trying to decide whether to continue manufacturing a part...
The management of Bramble Manufacturing Company is trying to decide whether to continue manufacturing a part or to buy it from an outside supplier. The part, called CISCO, is a component of the company’s finished product. The following information was collected from the accounting records and production data for the year ending December 31, 2017. 1. 8,100 units of CISCO were produced in the Machining Department. 2. Variable manufacturing costs applicable to the production of each CISCO unit were:     direct...