Question

The total cost, excluding normal time labor costs, for Plan A = $105,000105,000. (Enter your response...

The total cost, excluding normal time labor costs, for Plan A =

$105,000105,000.

(Enter your response as a whole number.)

Plan B: Vary the workforce to produce the prior month's demand. The firm produced

1 comma 3001,300

units in June. The cost of hiring additional workers is

$3030

per unit produced. The cost of layoffs is

$6060

per unit cut back.

(Enter

all responses as whole numbers.)

Note: Both hiring and layoff costs are incurred in the month of the change (i.e., going from production of

1 comma 3001,300

in July to

12001200

in August requires a layoff (and related costs) of

100100

units in August).

Month

Demand

Production

Hire

(Units)

Layoff

(Units)

Ending Inventory

Stockouts

(Units)

1

July

12001200

nothing

nothing

nothing

nothing

nothing

2

August

13001300

nothing

nothing

nothing

nothing

nothing

3

September

12001200

nothing

nothing

nothing

nothing

nothing

4

October

17001700

nothing

nothing

nothing

nothing

nothing

5

November

16501650

nothing

nothing

nothing

nothing

nothing

6

December

16501650

nothing

nothing

nothing

nothing

nothing

The total hiring cost =

$nothing.

(Enter your response as a whole number.)

The total layoff cost =

$nothing.

(Enter your response as a whole number.)

The total inventory carrying cost =

$nothing.

(Enter your response as a whole number.)

The total stockout cost =

$nothing.

(Enter your response as a whole number.)

The total cost, excluding normal time labor costs, for Plan B =

$nothing.

(Enter your response as a whole number.)

Homework Answers

Answer #1

Formula:

D4 =C3

E4 =MAX(0,D4-D3)

F4 =MAX(0,D3-D4)

G4 =MAX(0,G3+D4-C4-H3)

H4 =MAX(0,-G3-D4+C4+H3)

copy these formulas down to row 9

F13 =E10*E11

F14 =F10*F11

F15 =G10*G11

F16 =H10*H11

F17 =SUM(F13:F16)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$20 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1 comma 000 units per month and subcontract additional units at a ?$70 per unit premium...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$30 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1,000 units per month and subcontract additional units at a ?$65 per unit premium cost. Subcontracting...
The president of Hill? Enterprises, Terri? Hill, projects the? firm's aggregate demand requirements over the next...
The president of Hill? Enterprises, Terri? Hill, projects the? firm's aggregate demand requirements over the next 8 months as? follows: January 1,500 May February 1,700 June 2,200 March 1,600 July 1,700 April 1,900 August 1,700 Her operations manager is considering a new? plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is ?$100per unit. Inventory holding cost is ?$20 per unit per month. Ignore any? idle-time costs. The plan is called plan...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you have 30 workers. It is not possible to hire any additional workers until next Summer, at which time temporary workers will be hired at the beginning of Summer and laid off at the end of Summer. Therefore, no hiring or laying...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For June and July you should produce to exact demand forecast. For August and September you should use overtime and inventory with a stable workforce. Stable means the number of workers needed for July will be held constant through September. However the Ministry of Labour regulations put a maximum of 5000 hours of overtime labour per month in August and September (Zero overtime in June...
An electronics firm is currently manufacturing an item that has a variable cost of $ 0.50...
An electronics firm is currently manufacturing an item that has a variable cost of $ 0.50 per unit and a selling price of $ 1.10 per unit. Fixed costs are $ 15 comma 000. Current volume is 30 comma 000 units. The firm can substantially improve the product quality by adding a new piece of equipment at an additional fixed cost of $ 6 comma 000. Variable cost would increase to $ 0.60​, but volume should jump to 50 comma...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Maryville, Inc., incurred the following costs during August: Raw materials used $ 32,900 Direct labor 78,600...
Maryville, Inc., incurred the following costs during August: Raw materials used $ 32,900 Direct labor 78,600 Manufacturing overhead, actual 45,300 Selling expenses 29,330 Administrative expenses 15,870 Interest expense 9,600 During the month, 5,600 units of product were manufactured and 4,700 units of product were sold. On August 1, Maryville, Inc., carried no inventories. On August 31, there were no inventories other than finished goods. Required: a. Calculate the cost of goods manufactured during August and the average cost per unit...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT