Please do it by type not pics.
You're at home, before you start your internship, your local city council heard you have experience in project management. They want to create a botanical garden in your city park and have asked you to create a PERT chart of the following tasks from their Work Breakdown Structure.
Code | Activity | Time (in hours) | Immediate Predecessor(s) |
A | Planning | 20 | None |
B | Purchasing | 60 | Planning |
C | Excavation | 100 | Planning |
D | Sawing | 30 | Purchasing |
E | Placement | 20 | Sawing, excavation |
F | Assembly | 10 | Placement |
G | Infill | 20 | Assembly |
H | Outfill | 10 | Assembly |
I | Decoratoin | 30 | Infill, outfill |
a. Using Activity-on-Node, create a precedence diagram of the
garden project?
b. using ES, EF, LS, LF, determine the critical path of this
project?
c. How long will this project take (in hours)?
d. One of the city planners insists that if they can reduce
purchasing by 20 hours, the project will be done sooner. Is he
correct? Why or why not?