One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for Items A, B, C, and D; lots of size 50 and 180 are used for Items E and F, respectively. Item C has an on-hand (beginning) inventory of 15; D has an on-hand inventory of 50; all other items have zero beginning inventories. Construct :
a) simple product structure tree and the low-level-coded BOM
b) indented and the summarized parts lists.
0 | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | ||
Gross Requirement | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | ||
Item A | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=0 | Proj. Available balance | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT=1 | Net requirement | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | |
SS=0 | Planned order receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 | |
Q=L4L | Planned order release | 0 | 0 | 0 | 0 | 0 | 0 | 20 | 0 | |
Gross Requirement | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 | ||
Item B | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=0 | Proj. Available balance | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT=2 | Net requirement | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 | |
SS=0 | Planned order receipt | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 | |
Q=L4L | Planned order release | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 0 | |
Gross Requirement | 0 | 0 | 0 | 0 | 0 | 0 | 60 | 0 | ||
Item C | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=15 | Proj. Available balance | 15 | 15 | 15 | 15 | 15 | 15 | 15 | 0 | 0 |
LT=1 | Net requirement | 0 | 0 | 0 | 0 | 0 | 0 | 45 | 0 | |
SS=0 | Planned order receipt | 0 | 0 | 0 | 0 | 0 | 0 | 45 | 0 | |
Q=L4L | Planned order release | 0 | 0 | 0 | 0 | 0 | 45 | 0 | 0 | |
Gross Requirement | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 0 | ||
Item E | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=0 | Proj. Available balance | 0 | 0 | 0 | 0 | 0 | 10 | 10 | 10 | 10 |
LT=2 | Net requirement | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 0 | |
SS=0 | Planned order receipt | 0 | 0 | 0 | 0 | 50 | 0 | 0 | 0 | |
Q=50 | Planned order release | 0 | 0 | 50 | 0 | 0 | 0 | 0 | 0 | |
Gross Requirement | 0 | 0 | 0 | 0 | 80 | 90 | 0 | 0 | ||
Item F | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=0 | Proj. Available balance | 0 | 0 | 0 | 0 | 0 | 100 | 10 | 10 | 10 |
LT=1 | Net requirement | 0 | 0 | 0 | 0 | 80 | 0 | 0 | 0 | |
SS=0 | Planned order receipt | 0 | 0 | 0 | 0 | 180 | 0 | 0 | 0 | |
Q=180 | Planned order release | 0 | 0 | 0 | 180 | 0 | 0 | 0 | 0 | |
Gross Requirement | 0 | 0 | 100 | 0 | 0 | 45 | 40 | 0 | ||
Item D | Scheduled receipt | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
OH=50 | Proj. Available balance | 50 | 50 | 50 | 0 | 0 | 0 | 0 | 0 | 0 |
LT=1 | Net requirement | 0 | 0 | 50 | 0 | 0 | 45 | 40 | 0 | |
SS=0 | Planned order receipt | 0 | 0 | 50 | 0 | 0 | 45 | 40 | 0 | |
Q=L4L | Planned order release | 0 | 50 | 0 | 0 | 45 | 40 | 0 | 0 |