Question

Suad? Alwan, the purchasing agent for Dubai? Airlines, has found that the fifth plane it needed...

Suad? Alwan, the purchasing agent for Dubai? Airlines, has found that the fifth plane it needed from a Brazilian manufacturer took that firm 16,000 hours to produce. Using an 80?% learning curve and a $20?-per-hour labor? charge, Suad wishes to calculate what twelve additional planes should cost.??

Time required for the twelfth unit? =

cost for the 12th unit=

Time required for the thirteenth unit? =

cost for thirteenth unit=

Time required for the fourteen unit=

cost of the fourteenth unit=

tme required for the fifteenth unit=

cost of the 15th unit=

combined time for all 4 planes=

combined cost of all 4 planes=

Homework Answers

Answer #1

Learning factor = ln(80%)/ln 2 = ln(0.8)/ln 2 = -0.321

Time to taken to complete first plane = 16000/(5^-0.321) = 26821.89 or 26822 hrs

Time to taken to complete 12th plane = 26822 * (12^-0.321)= 12080.19 or 12080 hrs
Time to taken to complete 13th plane = 26822 * (13^-0.321)= 11773.76 or 11774 hrs
Time to taken to complete 14th plane = 26822 * (14^-0.321)= 11496.98 or 11497 hrs
Time to taken to complete 15th plane = 26822 * (15^-0.321)= 11245.16 or 11245 hrs

Cost for 12th plane = 20*12080 = $241600
Cost for 12th plane = 20*11774 = $235480
Cost for 12th plane = 20*11497 = $229940
Cost for 12th plane = 20*11245 = $224900

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT