Question

An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25,...

An end item’s demand forecasts for the next 10 weeks are 30, 20, 35, 50, 25, 25, 0, 40, 0, and 50 units. The current on-hand inventory is 80 units. The order policy is to produce in lots of 100. The booked customer orders for the item, starting with week 1, are 22, 30, 15, 9, 0, 0, 5, 3, 7, and 0 units. At present, no MPS quantities are on-hand for this item. The lead time is 2 weeks. Develop an MPS for this end item.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for...
Shown below is a partially completed MPS record for ball bearings. a. Develop the MPS for ball bearings. ?(Enter your responses as integers. A response of? "0" is equivalent to being not? applicable.) ?Item: Ball bearings Order? Policy: 500 units Lead? Time: 1 week Quantity on? Hand: 400 Week 1 2 3 4 5 6 7 8 9 10 Forecast 550 300 350 400 300 400 150 300 400 350 Customer orders? (booked) 300 350 250 250 150 150 150...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item lead time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
TASK:   Complete the MRP record for component C as it would appear at the beginning of...
TASK:   Complete the MRP record for component C as it would appear at the beginning of week 2. MRP record for component C as it would appear at the beginning of week 1. Week 1 2 3 4 5 6 Gross Requirements 15 30 25 25 10 20 Scheduled Receipts 40 0 0 0 0 0 Projected Available Balance 50 20 35 10 0 20 Planned Order Receipts 0 0 40 0 0 40 Planned Order Releases 40 0 0...
Problem 5 Eighty units of end item E are needed at the beginning of week 6....
Problem 5 Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of J have been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5. Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 units of B and 20 units of J now on hand. Lead times...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small...
Week 4 Exercise (Sales & Operations planning) – for 3% of the total grade A small company produces a variety of recreational and leisure vehicles. The sales & marketing manager has developed the following aggregate forecasts: Month Mar Apr May Jun Jul Aug Sep Forecast 50 44 55 80 70 40 50 Use the following information: Regular labor cost                  $240 per unit Overtime labor cost                $360 per unit Subcontracting cost                $400 per unit Regular capacity                     50 units per month Overtime...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of...
Question 5: Forecasting (8 p) The table below shows the demand (in units per quarter) of a specific product in the past three years. Quarter Year 1 2 3 4 2015 350 254 176 228 2016 367 258 169 236 2017 342 250 166 228 Predict demand in quarter 1 and quarter 2 of 2018, given that the demand forecast for the whole year is a total of 1,040 units. Question 6: DRP (8 p) A central DC supplies a...
The Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal...
The Silver Star Bicycle Company will be manufacturing both men’s and women’s models of its Easy-Pedal 10-speed bicycles during the next two months. Management wants to develop a production schedule indicating how many bicycles of each model should be produced in each month. Current demand forecasts call for 150 men’s and 125 women’s models to be shipped during the first month and 200 men’s and 150 women’s models to be shipped during the second month. Additional data are shown: Production...
1. The use of a production smoothing strategy creates inventory for products that experience a seasonal...
1. The use of a production smoothing strategy creates inventory for products that experience a seasonal fluctuation in demand.   True or False ? 2. Companies belonging to the same industry segment should have the same inventory turns.  True or False ? 3. Which of the following is a work-in-process inventory for C&A Bakery? A. Flour B. Cupcakes freshly out of the oven C. Ovens D. Cupcake mix prepared from scratch 4. C&A has on average $6000 in inventory and its daily...