Question

United Express Service (UES) uses large quantities of packaging materials at its four distribution hubs. After...

United Express Service (UES) uses large quantities of packaging materials at its four distribution hubs. After screening potential suppliers, UES identified six vendors that can provide packaging materials that will satisfy its quality standards. UES asked each of the six vendors to submit bids to satisfy annual demand at each of its four distribution hubs over the next year. The following table lists the bids received (in thousands of dollars). UES wants to ensure that each of the distribution hubs is serviced by a different vendor. Which bids should UES accept, and which vendors should UES select to supply each distribution hub?

Distribution Hub
Bidder 1 2 3 4
Martin Products 185 180 130 235
Schmidt Materials 150 240 145 215
Miller Containers 220 225 140 240
D&J Burns 165 185 185 275
Larbes Furnishings 210 180 145 240
Lawler Depot 235 195 140 255
Bidder Decision Bid
Martin Products
Schmidt Materials
Miller Containers
D&J Burns
Larbes Furnishings
Lawler Depot

The value of the objective function is _______ thousands of dollars.

Homework Answers

Answer #1

This problem will be solved using binary decision variables.

The variables are defined in the table below. It means that if a11 = 1 then Martin Products will service 1st distribution hub. If it is 0 then it will not service the hub.

1 2 3 4
Bidder
Martin Products a11 a12 a13 a14
Schimdt Materials b11 b12 b13 b14
Miller Containers c11 c12 c13 c14
D&J Burns d11 d12 d13 d14
Larbes Furnishings e11 e12 e13 e14
Lawler Depot f11 f12 f13 f14

Objective function: 185a11+180a12+130a13+235a14+150b11+240b12+145b13+215b14+220c11+225c12+140c13+240c14+165d11+185d12+185d13+275d14+210e11+180e12+145e13+240e14+235f11+195f12+140f13+255f14

This has to be minimized.

Constraints:

1. a11+a12+a13+a14<=1

2. b11+b12+b13+b14<=1

3. c11+c12+c13+c14<=1

4. d11+d12+d13+d14<=1

5. e11+e12+e13+e14<=1

6. f11+f12+f13+f14<=1

7. a11+b11+c11+d11+e11+f11 = 1

8. a12+b12+c12+d12+e12+f12 = 1

9. a13+b13+c13+d13+e13+f13 = 1

10. a14+b14+c14+d14+e14+f14 = 1

11. all variables are binary.

The excel's solver function gives the following solution:

Variable values (as computed by excel's solver)
1 2 3 4
Bidder
Martin Products 0 0 1 0
Schimdt Materials 0 0 0 1
Miller Containers 0 0 0 0
D&J Burns 1 0 0 0
Larbes Furnishings 0 1 0 0
Lawler Depot 0 0 0 0
1 2 3 4
Bidder
Martin Products 185.00 180.00 130.00 235.00
Schimdt Materials 150.00 240.00 145.00 215.00
Miller Containers 220.00 225.00 140.00 240.00
D&J Burns 165.00 185.00 185.00 275.00
Larbes Furnishings 210.00 180.00 145.00 240.00
Lawler Depot 235.00 195.00 140.00 255.00
Formula
Total cost 690.00 185a11+180a12+130a13+235a14+150b11+240b12+145b13+215b14+220c11+225c12+140c13+240c14+165d11+185d12+185d13+275d14+210e11+180e12+145e13+240e14+235f11+195f12+140f13+255f14
Constraints
1 <= 1 a11+a12+a13+a14<=1
1 <= 1 b11+b12+b13+b14<=1
0 <= 1 c11+c12+c13+c14<=1
1 <= 1 d11+d12+d13+d14<=1
1 <= 1 e11+e12+e13+e14<=1
0 <= 1 f11+f12+f13+f14<=1
1 = 1 a11+b11+c11+d11+e11+f11 = 1
1 = 1 a12+b12+c12+d12+e12+f12 = 1
1 = 1 a13+b13+c13+d13+e13+f13 = 1
1 = 1 a14+b14+c14+d14+e14+f14 = 1

Required solution table:

Bidder Decision Bid
Martin Products Select 130
Schmidt Materials Select 215
Miller Containers Reject Not applicable as bidder is not selected
D&J Burns Select 165
Larbes Furnishings Select 180
Lawler Depot Reject Not applicable as bidder is not selected

The value of the objective function is 690 thousands of dollars.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT