Question

Below are the project steps for the creation of a television advertisement for Foolio, which is...

Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5:

Activity

Duration (days)

Description

Preceding Activity(ies)

A

6

Create script for advertisement

-

B

4

Book technical crew

A

C

4

Book actors

A

D

3

Create props and costumes

B,C

E

6

Book location

C

F

5

Filming and editing

D,E

How many paths are there through this network?

1

2

3

4

How many critical paths are there?

0

1

2

3

Which activities have slack?

A

B

E

F

What is the slack for activity B?

0

1

2

3

What is the expected duration of this project?

19

20

21

22

Which of the following statements about a network’s critical path(s) is always true?

The critical path(s) is the path that passes through the most activities

The critical path(s) is the path with longest total time duration

The critical path(s) is the path that passes through the most slack activities

The critical path(s) is the path that gets us through the network fastest.

In these network diagrams, slack is best described a measurement of what?

The difference between an activity’s normal cost and its crash cost

The difference between an activity’s early start and early finish times

The difference between the duration of two precedent activities

The difference between an activity’s early start and late start times

Homework Answers

Answer #1

-------------------------------------------

How many paths are there through this network?

[3] - ABDF, ACDF, ACEF

How many critical paths are there?

[1] - ACEF with duration of 21 days

Which activities have slack?

[B] - because others are on the critical path and hence have slack=0

----------------------------------

Activity Duration
(days)
Predecessors ES EF LS LF Slack
A 6 - 0 6 0 6 0
B 4 A 6 10 9 13 3
C 4 A 6 10 6 10 0
D 3 B,C 10 13 13 16 3
E 6 C 10 16 10 16 0
F 5 D,E 16 21 16 21 0

-----------------------------------------

What is the slack for activity B?

[3]

What is the expected duration of this project?

[21]

Which of the following statements about a network’s critical path(s) is always true?

[The critical path(s) is the path with longest total time duration]

In these network diagrams, slack is best described a measurement of what?

[The difference between an activity’s early start and late start times]

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly...
Question 8 of 21 Gantt charts are effective for project scheduling if: A. Activities are highly interconnected B. Activity times are random C. The project contains simple activity sequences D. All of the above Reset Selection Question 9 of 21 Which of the following is NOT included in project control? A. Monitoring costs, time, and performance B. Adhering to the budget C. Correcting the plan as necessary D. All of the above are included Reset Selection Question 10 of 21...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity...
Consider the following information for a project to add a drive-thru window at Crestview Bank.       Activity Activity Time​ (weeks) Immediate​ Predecessor(s) A 6 − B 1 − C 9 − D 3 ​A, B E 6 B F 4 ​D, C G 5 ​E, C H 9 ​F, G b. Specify the critical path. The critical path is _____ and the project duration is_____ c. Calculate the slack for activities A and D.
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Good project management allows firms to efficiently create products and services for local markets and to...
Good project management allows firms to efficiently create products and services for local markets and to respond effectively to competitive local markets. True False The critical path is a continuous path through the project network that 1. Starts at the first activity in the project 2. Terminates at the last activity in the project 3. Includes only activities with a slack more than zero. True False To create goods and services, all organizations perform three functions: Marketing, Production/operations, and Finance/accounting....
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine...
Question: To complete the wing assembly for and experimental aircraft, Jim Gilbert has laid out nine activities involved. These activities have been labeled A through I in the following table. The company is planning to finish the project in 34 weeks. Please answer the following questions. Determine the expected (estimated) duration and variance for each activity. You can round the expected duration numbers without decimals. Activity Immediate Predecessor(s) Optimistic Probable Pessimistic Expected duration Variance A -- 5 9 13 Answer...