Question

Management Instructions                                      &nbs

Management Instructions                                                                                         

            -          Ending inventory target for Period 5                                                             

            -          Backorder maximum if possible (after the first period)                                                                  

                        Regular shift production per employee per period                                                               

                        The company's production strategy keeps the regular shift fully utilized                                                               

            40       Maximum overtime production per period if needed                                               Use Overtime before Subcontractors           

            10       Maximum subcontractor production per period if needed                                                               

            32       Initial inventory                                                                      

                                                                                               

                                                                                               

Aggregate Plan                                                                                              

                                    1          2          3          4          5          Totals

Forecast                                  240     245     235     190     290    

Employees                                                                                         

                                                                                               

Output                                                                                    

            Regular                       220     220     220     220     220    

            Overtime                                                                                

            Subcontractor                                                                        

Output - Forecast                                                                                          

                                                                                               

Inventory                                                                                            

            Beginning                                                                               

            Ending                                                                        

            Average                                                                                  

Backlog                                                                                              

                                                                                               

Costs                                                                                      

            Regular           $298.00                                                                     

            Overtime         $347.00                                                                     

            Subcontractor $410.00                                                                     

            Hire / Layoff    $885.00                                                                     

            Inventory         $65.00                                                                       

            Backlog           $75.00                                                                       

                                                                                               

Total Costs     

                                                                                   

Perform the necessary calculations for a Match (Chase) Production Strategy

What is the Backlog quantity for Period 3?

What is the Backlog for Period 5?

What is the Output - Forecast Quantity for Period 2?

What is the Beginning Inventory quantity for Period 2?

What is the Beginning Inventory quantity for Period 5?

What is the cost of Overtime Production in Period 1?

What is the Cost of Inventory for Period 3?

What is the Total Cost of Period 4?

What is the cost of Backlog for Period 5?

What is the Average Inventory in Period 4?

Homework Answers

Answer #1

Chase plan is following:

Formulas:

1 Period 2 Forecast Total 1200 245 12 240 235 190 290 Em 10 4 Output Regular Overtime Subcontract 200 180 280 10 240 240 1140 32 32 8 Output Forecast 9 Invento 10 32 Beginning Ending Average 12 13 Backlo 14 Costs 15 16 17 18 Hire/Layoff 19 Invento 20 Back orders 21 Total 16 21 Regular Overtime Subcontract 298.0059,600 71,5071,52053,64083,440339,720 9,716 347.002,7761,735 410.00 885.00 2 2 01,735 3,470 0 8,850 1,770 02,655 4,425 17,700 1,365 65.001,040 75.00 163 163 72,266 75,025 71,68358,19391,335368,501 24

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Management Instructions                                      &nbs
Management Instructions                                                                                                      -          Ending inventory target for Period 5                                                                          -          Backorder maximum if possible (after the first period)                                                                               32       Regular shift production per employee per period                                                                                        The company's production strategy keeps the regular shift fully utilized                                                                            100     Maximum overtime production per period if needed                                               Use Overtime before Subcontractors                        35       Maximum subcontractor production per period if needed                                                                            42       Initial inventory                                                                                                                                                                                                                                                                       Aggregate Plan                                                                                                                                   1          2          3         ...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Period Forecast 1 200 2 500 3 300 4 400 5 200 6 200 Regular time:...
Period Forecast 1 200 2 500 3 300 4 400 5 200 6 200 Regular time: $20 per unit (maximum of 280 units per period) Overtime:    $30 per unit (maximum of 40 units per period) Subcontracting:    Not available Beginning inventory:   None Carrying cost: $10 per unit per period Backorder cost: $50 per unit per period What is the first period in which overtime should be scheduled in order to minimize total cost for the aggregate plan?
Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you have 30 workers. It is not possible to hire any additional workers until next Summer, at which time temporary workers will be hired at the beginning of Summer and laid off at the end of Summer. Therefore, no hiring or laying...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory,...
Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time and overtime, subcontracting and backorders. The plan must wind up with no units in ending inventory in Period 6. Regular time capacity is 150 units per month. Overtime capacity and subcontracting capacity are 20 units per month each. Overtime cost is $30 per unit, subcontracting cost is 40 per unit, and backorder cost is $20 per unit, inventory holding cost is $5...
#2 Given the following forecast and steady regular output of 550 every month, what total cost...
#2 Given the following forecast and steady regular output of 550 every month, what total cost would result if overtime is limited to a maximum of 50 units a month, and subcontracting is limited to a maximum of 10 units a month? Unit costs are: Regular output $20 Overtime $30 Subcontract $25 Average Inventory $10 Backlog $18 Month 1 2      3      4       5       6 Forecast           540   540   570   590   600   580
Neal Industries manufactures blue jeans for the teen market. The S&OP team has agreed upon a...
Neal Industries manufactures blue jeans for the teen market. The S&OP team has agreed upon a demand forecast for the following year, as shown below. The company begins with 1,800,000 jeans in safety stock and desires to maintain this level consistently (and end with this level), assume that the overtime production wage rate is $24 per hour. Quarter Demand 1 7,500,000 2 8,300,000 3 15,000,000 4 12,500,000 Current workforce 300 workers Average output per worker 25,000 jeans per quarter Inventory...
Planners for a firm are about to prepare the aggregate plan for one particular product that...
Planners for a firm are about to prepare the aggregate plan for one particular product that will cover the next six periods. Demand over those six periods is expected to be: 250, 200, 400, 500, 550, and 300 for total demand of 2,200. They have regular time capacity of 350 units per period and they plan to produce that many each period. They have unlimited overtime capacity. They wil only produce in overtime to prevent a backorder/backlog. They realize that...
While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging...
While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging in the market. In response, the management at Fabric Mills quickly bumped up the regular output of medical-grade fabric by reassigning workers from the production of regular fabric and rehiring retired workers. Table 2 shows the demand forecast and capacity for medical-grade fabric. Note that overtime is limited to 20% of the regular capacity. The availability of subcontract is also limited due to the...