Question

for the following data, calculate the number of workers required for level production and the resulting...

for the following data, calculate the number of workers required for level production and the resulting month-end inventories. Each worker can produce 14 units per day, and thee desired ending inventory is 9000 units.

Month May June Jul Aug Total

Working Days 20 24 12 19 ________

Forecast Demand 2800 27500 28500 28500 _________

Planned Production ____-___ ______ ______ ______ _________

Planned Inventory 11,500 ______ ______ _______ _________

Homework Answers

Answer #1

Level production is a strategy in which

  • we maintain constant level of employees without hiring and firing
  • we can use over time and under time

Total Production required

= 112,500 + 9000 – 11,500

= 110,000 Units

Daily Production required

= 110,000 ÷75

= 1466.67 Units

Number of workers required

= 1466.67/14

=104.76 or

105 workers

Actual number of units produced daily

= 105 x 14

= 1470 units

  • Planned production for a month= 1470 * Number of working days in the month
  • Beginning inventory of a month = ending inventory of previous month
  • Ending inventory of a month = Beginning inventory of the month+ Planned production for the month – Demand

                                                                       

Month

May

June

July

August

Total

Working Days

20

24

12

19

75

Forecast Demand

28,000

27,500

28,500

28,500

1,12,500

Planned Production

29,400

35,280

17,640

27,930

1,10,250

Planned Inventory

11,500

12,900

20,680

9,820

9,250

Note

  • Here the period is day
  • The ending inventory is actually slightly higher than desired level

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Develop a production schedule to produce the exact production requirements by varying the workforce size for...
Develop a production schedule to produce the exact production requirements by varying the workforce size for the following problem. The monthly forecasts for Product X for January, February, and March are 950, 1,510, and 1,220, respectively. Safety stock policy recommends that half of the forecast for that month be defined as safety stock. There are 22 working days in January, 19 in February, and 21 in March. Beginning inventory is 550 units. Storage cost is $4 per unit per month...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Plan production for a four-month period: February through May. For February and March, you should produce...
Plan production for a four-month period: February through May. For February and March, you should produce to exact demand forecast. For April and May, you should use overtime and inventory with a stable workforce; stable means that the number of workers needed for March will be held constant through May. However, government constraints put a maximum of 5,000 hours of overtime labor per month in April and May (zero overtime in February and March). If demand exceeds supply, then backorders...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For...
Question 4: Aggregate Planning Plan production for a four month period: June through to September. For June and July you should produce to exact demand forecast. For August and September you should use overtime and inventory with a stable workforce. Stable means the number of workers needed for July will be held constant through September. However the Ministry of Labour regulations put a maximum of 5000 hours of overtime labour per month in August and September (Zero overtime in June...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is...
Develop a production plan and calculate the annual cost for a firm whose demand forecast is fall, 10,000; winter, 8,000; spring, 7,000; summer, 12,000. Inventory at the beginning of fall is 500 units. At the beginning of fall, you have 30 workers. It is not possible to hire any additional workers until next Summer, at which time temporary workers will be hired at the beginning of Summer and laid off at the end of Summer. Therefore, no hiring or laying...
In order to effectively address the seasonal variation appearing in the annual demand of its products,a...
In order to effectively address the seasonal variation appearing in the annual demand of its products,a bicycle manufacturer starts an aggregate planning.A planning hori- zon of 6 months is used. The (aggregate) demand forecast for the next six months along the number of working days are given below: Month Demand Forcast Number of Working Days Jan 1800 22 Feb 1500 19 Mar 1100 21 apr 900 21 may 1100 22 june 1600 20 If the manufacturer operates 300 days a...
On January 1, 2020, the Hardin Company budget committee has reached agreement on the following data...
On January 1, 2020, the Hardin Company budget committee has reached agreement on the following data for the 6 months ending June 30, 2020. Sales units: First quarter 5,400; second quarter 7,000; third quarter 7,600. Ending raw materials inventory: 40% of the next quarter’s production requirements. Ending finished goods inventory: 25% of the next quarter’s expected sales units. Third-quarter production: 7,840 units. The ending raw materials and finished goods inventories at December 31, 2019, follow the same percentage relationships to...
Shoney Video Concepts produces a line of videodisc players to be linked to personal computers for...
Shoney Video Concepts produces a line of videodisc players to be linked to personal computers for video games. Videodiscs have much faster access time than tape. With such a computer/video link, the game becomes a very realistic experience. In a simple driving game where the joystick steers the vehicle, for example, rather than seeing computer graphics on the screen, the player is actually viewing a segment of a videodisc shot from a real moving vehicle. Depending on the action of...
AGENDA: PROFIT PLANNING (BUDGETING) Building a master budget. 1. Sales budget 2. Production budget 3. Direct...
AGENDA: PROFIT PLANNING (BUDGETING) Building a master budget. 1. Sales budget 2. Production budget 3. Direct materials budget 4. Direct labor budget 5. Manufacturing overhead budget 6. Ending finished goods inventory budget 7. Selling and administrative expenses budget 8. Cash budget 9. Budgeted income statement 10. Budgeted balance sheet OVERVIEW OF BUDGETING A budget is a detailed plan for acquiring and using financial and other resources over a specified period. Budgeting involves two stages: • Planning: Developing objectives and preparing...
Question 16 Helton Company has the following information for the current year: Beginning fixed manufacturing overhead...
Question 16 Helton Company has the following information for the current year: Beginning fixed manufacturing overhead in inventory $95,000 Fixed manufacturing overhead in production 375,000 Ending fixed manufacturing overhead in inventory 25,000 Beginning variable manufacturing overhead in inventory $10,000 Variable manufacturing overhead in production 50,000 Ending variable manufacturing overhead in inventory 15,000 What is the difference between operating incomes under absorption costing and variable costing? Select one: A. $5,000 B. $65,000 C. $70,000 D. $50,000 E. $40,000 Question 17 A...