Question

Mary Kate is a project manager in the IT department for a university. She has been...

Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment.

Mary Kate performed the following steps to begin the intranet project.

She performed a needs analysis. Mary Kate interviewed the university faculty to determine their needs for an intranet and the uses they foresee for it. She discovered that several of the professors were working on a research project and wanted to use the intranet to facilitate group discussions, as well as to host periodic Webinars for professors at other universities.

She chose the project team. Mary Kate enlisted members of the IT department for the project, including someone to install firewalls so users have more secure access to the Internet, and someone to set up the site to host Webinars.

She determined the project constraints. Mary Kate determined when the intranet needed to be live. She considered how long she would have the services of the various team members, how long team members could work on this project before being assigned to other tasks, and when the first Webinar was scheduled. Once she gathered all of this information, she was able to determine the project scope and constraints.

She created the project schedule. Mary Kate worked with the project team to outline the tasks and task relationships required to complete the project. She assigned resources to specific tasks so that each person was aware of his or her role in the overall project plan.

She scheduled weekly meetings for the duration of the project. Mary Kate included the CIO, project team members, faculty members and all other stakeholders in the meetings.

She created a project status report and an issues log. Mary Kate used these documents in each meeting to apprise stakeholders of the project's progress and to introduce any problems or issues that had arisen since the last meeting.

Once Mary Kate had performed all these tasks, she was ready to begin the executing phase of the project.

What tasks might Mary Kate perform in the executing phase? In the controlling phase? In the closing phase?

Homework Answers

Answer #1

Tasks might Mary Kate to perform in the executing phase

In the Executing phase where deliverables are developed and completed. This often feels like the meat of the project since a lot is happening during this time, like status reports and meetings, development updates, and performance reports. A “kick-off” meeting usually marks the start of the Project Execution phase where the teams involved are informed of their responsibilities.

Tasks completed during the Execution Phase include:

·         Develop team

·         Assign resources

·         Execute project management plans

·         Procurement management if needed

·         PM directs and manages project execution

·         Set up tracking systems

·         Task assignments are executed

  • Status meetings
  • Update project schedule
  • Modify project plans as needed

Tasks might Mary Kate to perform in the controlling phase

This is all about measuring project progression and performance and ensuring that everything happening aligns with the project management plan. Project managers will use key performance indicators (KPIs) to determine if the project is on track. A PM will typically pick two to five of these KPIs to measure project performance:

·         Project Objectives: Measuring if a project is on schedule and budget is an indication if the project will meet stakeholder objectives.

·         Quality Deliverables: This determines if specific task deliverables are being met.

·         Effort and Cost Tracking: PMs will account for the effort and cost of resources to see if the budget is on track. This type of tracking informs if a project will meet its completion date based on current performance.

·         Project Performance: This monitors changes in the project. It takes into consideration the amount and types of issues that arise and how quickly they are addressed. These can occur from unforeseen hurdles and scope changes.

During this time, PMs may need to adjust schedules and resources to ensure the project is on track

Tasks might Mary Kate to perform in the closing phase

This phase represents the completed project. Contractors hired to work specifically on the project are terminated at this time. Valuable team members are recognized. Some PMs even organize small work events for people who participated in the project to thank them for their efforts. Once a project is complete, a PM will often hold a meeting – sometimes referred to as a “post mortem” – to evaluate what went well in a project and identify project failures. This is especially helpful to understand lessons learned so that improvements can be made for future projects.

Once the project is complete, PMs still have a few tasks to complete. They will need to create a project punch list of things that didn’t get accomplished during the project and work with team members to complete them. Perform a final project budget and prepare a final project report. Finally, they will need to collect all project documents and deliverables and store them in a single place.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working...
Sydney was a newly hired project manager at a consulting firm. She has previous experience working on project teams but had never led a project on her own. She has only been with the firm for two weeks and has spent a week of that time in onboarding. Her manager, the head of operations, has just assigned her to a rather large project. The project is to evaluate the current processes in use within the organization specifically focused in two...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal news....
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT