Question

Mary Kate is a project manager in the IT department for a university. She has been...

Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment.

Mary Kate performed the following steps to begin the intranet project.

She performed a needs analysis. Mary Kate interviewed the university faculty to determine their needs for an intranet and the uses they foresee for it. She discovered that several of the professors were working on a research project and wanted to use the intranet to facilitate group discussions, as well as to host periodic Webinars for professors at other universities.

She chose the project team. Mary Kate enlisted members of the IT department for the project, including someone to install firewalls so users have more secure access to the Internet, and someone to set up the site to host Webinars.

She determined the project constraints. Mary Kate determined when the intranet needed to be live. She considered how long she would have the services of the various team members, how long team members could work on this project before being assigned to other tasks, and when the first Webinar was scheduled. Once she gathered all of this information, she was able to determine the project scope and constraints.

She created the project schedule. Mary Kate worked with the project team to outline the tasks and task relationships required to complete the project. She assigned resources to specific tasks so that each person was aware of his or her role in the overall project plan.

She scheduled weekly meetings for the duration of the project. Mary Kate included the CIO, project team members, faculty members and all other stakeholders in the meetings.

She created a project status report and an issues log. Mary Kate used these documents in each meeting to apprise stakeholders of the project's progress and to introduce any problems or issues that had arisen since the last meeting.

Which steps already performed by Mary Kate are part of the initiating phase for this project? Which steps are part of the planning phase?

Homework Answers

Answer #1

1) Which steps already performed by Mary Kate are part of the initiating phase for this project?

She created the project schedule. Mary Kate worked with the project team to outline the tasks and task relationships required to complete the project. She assigned resources to specific tasks so that each person was aware of his or her role in the overall project plan.'

She determined the project constraints. Mary Kate determined when the intranet needed to be live. She considered how long she would have the services of the various team members, how long team members could work on this project before being assigned to other tasks, and when the first Webinar was scheduled. Once she gathered all of this information, she was able to determine the project scope and constraints.

2)Which steps are part of the planning phase?

She performed a needs analysis. Mary Kate interviewed the university faculty to determine their needs for an intranet and the uses they foresee for it. She discovered that several of the professors were working on a research project and wanted to use the intranet to facilitate group discussions, as well as to host periodic Webinars for professors at other universities.

She scheduled weekly meetings for the duration of the project. Mary Kate included the CIO, project team members, faculty members and all other stakeholders in the meetings.

  

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Mary Kate is a project manager in the IT department for a university. She has been...
Mary Kate is a project manager in the IT department for a university. She has been asked to manage a project to create a faculty intranet. The university has multiple campuses in various locations, and professors and other faculty need to be able to easily post questions, schedules and other documents to share in a secure environment. Mary Kate performed the following steps to begin the intranet project. She performed a needs analysis. Mary Kate interviewed the university faculty to...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do...
Case Scenario LSS is engaged in flood relief support nationally and has been asked to do several international Camp Noah projects. Last year the French government asked for resources for children in Southeastern France who had been affected by floods; LSS responded within 15 weeks with a French Camp Noah curriculum that met many of the project objectives. The Board of Directors of LSS commended the effort; international expansion was added to this year’s strategic objectives for the LSS organization....
Case Study 1: A Day in the Life Rachel, the project manager of a large information...
Case Study 1: A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal...
(Use the case of “Global Treps”) You have been selected as the project manager for the...
(Use the case of “Global Treps”) You have been selected as the project manager for the Global Treps project. You helped to run a local shark tank like event at your college last year as part of a class project, so you have a general idea of what is involved. The schedule goal is six months, and the budget is $120,000. Your favorite professor, Dr. K., and a few of her associates have agreed to fund the project. Your strengths...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems...
Case Study 1:  A Day in the Life Rachel, the project manager of a large information systems project, arrives at her office early to get caught up with work before her co- workers and project team arrive. However, as she enters the office she meets Neil, one of her fellow project managers, who also wants to get an early start on the day. Neil has just completed a project overseas. They spend 10 minutes socializing and catching up on personal news....
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working...
Project Management Fundamentals Questions Only A project team is discussing the benefits and drawbacks of working on projects within their organization now that it has become project-oriented. They can agree on many advantages for the team and for the organization, but also agree there are some drawbacks, relative to the strong matrix structure the organization used to have. In a project-oriented organization the project team: ANSWER Will not always have a "home" Reports to the functional manager Has no loyalty...
Which of the following best describes a project management plan? The project charter, WBS, and project...
Which of the following best describes a project management plan? The project charter, WBS, and project scope statement The schedule, management plans, and budget A formal, approved document used to control the project The project manager's plan for managing and controlling the work The engineering department wants the project objective to be a 10 percent improvement in throughput. The information technology department wants no more than 5 percent of its resources to be used on the project. Management, who is...
CASE STUDY – Jacobson Carpet Company In January 2002, Ms. Mary Lewis was preparing to meet...
CASE STUDY – Jacobson Carpet Company In January 2002, Ms. Mary Lewis was preparing to meet with Mr. Carpenter, President of Jacobson Carpet Company. Ms. Lewis assumed that the meeting was related to the recent Board of directors of the company. As a direct assistant to the President, she knew from experience that this type of meeting often resulted in a project to be studied. Her expectation was confirmed as soon as Mr. Carpenter began to inform her of the...