Consider the following data for a project to install a new server at the Northland Pines High School
A |
4 | / |
B |
3 |
A |
C |
6 |
A |
D |
4 |
B |
E |
1 |
B |
F |
6 |
B, C |
G |
3 |
D, E |
H |
3 |
F |
I |
5 |
F |
J |
7 |
G, H, I |
How much slack is in each of the activities G, H, and I?
The Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity can be computed using the following formulae.
Forward pass
ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate
predecessors)
EF of an activity = Its ES + Its duration
Backward pass
LF of ending activities = Their EF
LF of all other activities = Min. (LS of their immediate
successors)
LS of an activity = Its LF - Its duration
Activity | Duration | Predecessor | ES | EF | LS | LF | Slack = LF - EF |
A | 4 | - | 0 | 4 | 0 | 4 | 0 |
B | 3 | A | 4 | 7 | 7 | 10 | 3 |
C | 6 | A | 4 | 10 | 4 | 10 | 0 |
D | 4 | B | 7 | 11 | 14 | 18 | 7 |
E | 1 | B | 7 | 8 | 17 | 18 | 10 |
F | 6 | B, C | 10 | 16 | 10 | 16 | 0 |
G | 3 | D, E | 11 | 14 | 18 | 21 | 7 |
H | 3 | F | 16 | 19 | 18 | 21 | 2 |
I | 5 | F | 16 | 21 | 16 | 21 | 0 |
J | 7 | G, H, I | 21 | 28 | 21 | 28 | 0 |
Slack of G, H, and I are 7, 2, and 0 respectively.
Get Answers For Free
Most questions answered within 1 hours.