Given below are the durations of and the precedence relationships among the activities required to compute a project.
1) construct an AOA network of the project
2)what is the critical path? determine the expected duration of the project.
3)compute the standard deviation of the critical path
Duration(days) | ||||
Activity | pre-decessor(s) | a | m | b |
A | - | 4 | 7 | 12 |
B | A | 6 | 9 | 13 |
C | A | 5 | 7 | 9 |
D | B,C | 3 | 5 | 8 |
E | B | 7 | 8 | 10 |
F | A | 2 | 3 | 5 |
G | E | 6 | 7 | 9 |
H | D,I | 2 | 3 | 4 |
I | F | 8 | 10 | 14 |
J | G,H | 4 | 6 | 10 |
Using PERT method
Activity | pre-decessor(s) | a | m | b | t = (a+4m+b)/6 |
A | - | 4 | 7 | 12 | 7.33 |
B | A | 6 | 9 | 13 | 9.17 |
C | A | 5 | 7 | 9 | 7.00 |
D | B,C | 3 | 5 | 8 | 5.17 |
E | B | 7 | 8 | 10 | 8.17 |
F | A | 2 | 3 | 5 | 3.17 |
G | E | 6 | 7 | 9 | 7.17 |
H | D,I | 2 | 3 | 4 | 3.00 |
I | F | 8 | 10 | 14 | 10.33 |
J | G,H | 4 | 6 | 10 | 6.33 |
The network diagram is drawn.
The critical activities will have slack = 0. Slack = LST - EST
The critcial path is A -> B -> E -> G - > J
The duration of the project is 38.17 days.
Only the Standard deviation of the critical activities accounts to the standard deviation of the entire project.
Activity | a | m | b | S.D = (b-a)/6 |
A | 4 | 7 | 12 | 1.33 |
B | 6 | 9 | 13 | 1.17 |
E | 7 | 8 | 10 | 0.50 |
G | 6 | 7 | 9 | 0.50 |
J | 4 | 6 | 10 | 1.00 |
Total S.D | 4.50 |
Get Answers For Free
Most questions answered within 1 hours.