Question

Given below are the durations of and the precedence relationships among the activities required to compute...

Given below are the durations of and the precedence relationships among the activities required to compute a project.

1) construct an AOA network of the project

2)what is the critical path? determine the expected duration of the project.

3)compute the standard deviation of the critical path

Duration(days)
Activity pre-decessor(s) a m b
A - 4 7 12
B A 6 9 13
C A 5 7 9
D B,C 3 5 8
E B 7 8 10
F A 2 3 5
G E 6 7 9
H D,I 2 3 4
I F 8 10 14
J G,H 4 6 10

Homework Answers

Answer #1

Using PERT method

Activity pre-decessor(s) a m b t = (a+4m+b)/6
A - 4 7 12 7.33
B A 6 9 13 9.17
C A 5 7 9 7.00
D B,C 3 5 8 5.17
E B 7 8 10 8.17
F A 2 3 5 3.17
G E 6 7 9 7.17
H D,I 2 3 4 3.00
I F 8 10 14 10.33
J G,H 4 6 10 6.33

The network diagram is drawn.

The critical activities will have slack = 0. Slack = LST - EST

The critcial path is A -> B -> E -> G - > J

The duration of the project is 38.17 days.

Only the Standard deviation of the critical activities accounts to the standard deviation of the entire project.

Activity a m b S.D = (b-a)/6
A 4 7 12 1.33
B 6 9 13 1.17
E 7 8 10 0.50
G 6 7 9 0.50
J 4 6 10 1.00
Total S.D 4.50
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C...
Path Activity to tm tp te=(to+4tm+tp)/6 Path total A-C-F-H A 3 4 5 4 19 C 2 3 10 4 F 3 5 7 5 H 2 6 10 6 B-D-F-H B 5 7 9 7 23 D 2 5 8 5 F 3 5 7 5 H 2 6 10 6 B-E-G B 5 7 9 7 21 E 1 7 7 6 G 7 8 9 8 The critical path is B-D-F-H. Hence, the expected duration of project...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
Given the data table below develop the precedence network and perform the CPM calculations. Then, using...
Given the data table below develop the precedence network and perform the CPM calculations. Then, using the proposed crashing strategy calculate the normal, least-cost, and crash duration for the project below. Calculate the cost associated with each duration. Indirect cost (overhead) is $120 per day. Activity IPA Duration Cost $ Normal Crash Normal Crash A - 5 4 $770 $900 B - 3 2 $660 $700 C A 7 4 $800 $1,070 D A,B 4 3 $1,000 $1,110 E B...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
A project manager, in preparation for the construction of roads, has identified the activities and their...
A project manager, in preparation for the construction of roads, has identified the activities and their durations to prepare a difficult stretch of motorway (as in the following table). Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D J 3 F K 8 E,H L 4 C,J (a) How long the project will take? (b) State the critical activities. (c)...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT