Question

Consider the following four--‐step assembly operation with quality problems. -The first resource has a processing time...

Consider the following four--‐step assembly operation with quality problems.

-The first resource has a processing time of 7 minutes per unit and one employee doing the operation

‐ The second resource has a processing time of 4 minutes per unit.  It also has one employee doing the operation. However, this is a very delicate task and 0.79 of all products have to be scrapped after this step.

‐ Two workers are staffed for the third resource. No quality problems occur at this resource and the processing time is 17minutes per unit.

‐ At the fourth and final resource, one operator handles the product. No quality problems exist at this step and the processing time is 12 minutes per unit.

What is the process capacity per hour? (keep two decimal)

Homework Answers

Answer #1

The time taken for 1st process is: 7 minutes per unit

The time taken for 2nd process is: 4 minutes per unit

  • As .79 of all the products are scrapped
  • .21 of all the products are passed to next process
  • Therefore we can say .21 of product take 4 minutes
  • So 1 product will take = 4/.21 = 19.05 minutes per unit

The time taken for 3rd process is: 17 minutes per unit

  • As there are 2 staff stationed so time taken for 3rd process is: 8.5 minutes per unit

The time taken for 4th process is: 12 minutes per unit

Now we can say bottle neck is process 2 which will define the capacity of the system

So process capacity per hour = 60/19.05 = 3.15 units

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Four Step Process with Rework and Scrap Consider the following four step assembly operation with quality...
Four Step Process with Rework and Scrap Consider the following four step assembly operation with quality problems. All resources are staffed with one operator. -The first resource has a processing time of 4 minutes per unit -The second resource has a processing time of 3 minutes per unit. This process suffers from a high yield loss and 50% of all products have to be scrapped after this step. -The third resource also suffers from quality problems. However, instead of scrapping...
The Big Manufacturing Company produces a particular product in an assembly line operation. One of the...
The Big Manufacturing Company produces a particular product in an assembly line operation. One of the machines on the line is a drill press that has a single assembly line feeding into it. A partially completed unit arrives at the press to be worked on every 7.5 minutes, on average. The machine operator can process an average of 10 parts per hour. Using the Poisson arrivals and exponential service time model, a-what is the average number of parts waiting to...
Lead Time Audio Max Electronics Company manufactures electronic stereo equipment. The manufacturing process includes printed circuit...
Lead Time Audio Max Electronics Company manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of assembly time. After each batch is completed,...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...
vThere are 3 steps in a laundry shop: i) Washing, ii) Drying, iii) Folding. If we...
vThere are 3 steps in a laundry shop: i) Washing, ii) Drying, iii) Folding. If we assume the time to do each load is 25, 50 and 35 minutes, respectively. We can assume that there is no variability in the process and all operations work fully efficiently. a) What is the Lead Time of the laundry shop? b) What is the Cycle Time? What is the throughput rate (loads per hour) of the laundry? c) What is the utilization %...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that...
Case Study 7-2 FIVE STAR TOOLS Five star tools is a small family -owned firm that manufactures diamond -coated cutting tools( chisels and saws) used by jewelers. Production involves three major processes. First, steel “ blanks” (tools without the diamond coating) are cut to size. Second, the blanks are sent to a chemical bath that prepares the tools for the coating process. In the third major process, the blanks are coated with diamond chips in a proprietary process that simultaneously...
How can differential analysis be applied here to determine if it would be profitable to invest...
How can differential analysis be applied here to determine if it would be profitable to invest in new equipment to increase capacity for a constrained resource? KRAYDEN’S CYCLE COMPONENTS INTRODUCTION: COMPANY, PRODUCT, AND SUPPLY CHAIN Krayden’s Cycle Components (KCC) is a high-end specialty fabricator that manufactures one product with many variants. The basic product is known as a rolling chassis, a key component used in manufacturing motorcycles. While there are variations across the industry, a rolling chassis typically consists of...
CASE STUDY ON LEADERSHIP/ Aidensfield hospital currently faces major problems with staff, management, general performance and...
CASE STUDY ON LEADERSHIP/ Aidensfield hospital currently faces major problems with staff, management, general performance and service quality. It is conceivable that these problems are related to the ‘leadership’ styles adapted by those in charge. The senior management have proposed some changes within the organisation to hopefully make improvements but making such decisions requires an in-depth understanding of what is going wrong and why. Leadership as a concept is often considered in isolation when in reality, it is coherent with...
Discussion Question: What would you do case? (CH10) DUE 5/6 The words “Cessna Skyhawk” have special...
Discussion Question: What would you do case? (CH10) DUE 5/6 The words “Cessna Skyhawk” have special meaning for anyone who has ever wanted to learn to fly. At 27 feet long and 8 feet tall, with a 36-foot wingspan, a 140 mph cruising speed, and room for two adults and their luggage, more people have learned to fly with a Cessna Skyhawk than with any other plane in aviation history. In fact, the Cessna Skyhawk is the best-selling plane of...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT