The critical path for the network activities shown below is
________ with duration ________.
Activity |
Duration |
Immediate |
A |
4 |
--- |
B |
2 |
A |
C |
7 |
-- |
D |
4 |
A |
E |
5 |
B,C,D |
Solution:
From the given information, network diagram can be drawn as below:
The possible paths in the network and their duration are computed below:
1) A - B - E = 4 + 2 + 5 = 11
2) A - D - E = 4 + 4 + 5 = 13 (longest path)
3) C - E = 7 + 5 = 12
Critical path in a network is the path with the longest duration. In the given network, the path with the longest duration is A-D-E. Hence, it is the critical path.
Critical path = A - D - E
Project duration = Length of the critical path
Length of the critical path = 13
Project duration = 13
Get Answers For Free
Most questions answered within 1 hours.