Question

The critical path for the network activities shown below is ________ with duration ________. Activity Duration...

The critical path for the network activities shown below is ________ with duration ________.

Activity

Duration

Immediate
Predecessors

A

4

---

B

2

A

C

7

--

D

4

A

E

5

B,C,D

Homework Answers

Answer #1

Solution:

From the given information, network diagram can be drawn as below:

The possible paths in the network and their duration are computed below:

1) A - B - E = 4 + 2 + 5 = 11

2) A - D - E = 4 + 4 + 5 = 13 (longest path)

3) C - E = 7 + 5 = 12

Critical path in a network is the path with the longest duration. In the given network, the path with the longest duration is A-D-E. Hence, it is the critical path.

Critical path = A - D - E

Project duration = Length of the critical path

Length of the critical path = 13

Project duration = 13

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 6 C A,B 7 D A,B 6 E A,B 8 F C,D,E 4 G C,D,E 3
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can...
A project has 6 activities (labelled A-F), with the following terms: Activity A and B can start at the same time, however Activity C can only start once Activity A ends Activity D can only start once Activity B and Activity C ends Activity E and Activity F can only start once Activity D ends The following table shows Durations for each activity Activity Duration (weeks) A 5 B 4 C 2 D 7 E 3 F 2 a. Draw...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...
Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D C 1 5 E B 2 5 F E 8 5 G D 10 5 H B 2 5 I B 3 5 J F,G,I 3 5 K H 2 5 L J,K 3 5 M L 1 5 i.Construct an activity on the arrow network ii. Determine the Duration of the Critical Path; iii. Draw the corresponding Gantt chart iv. Draw the resource...
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There...
Q1. Which of the following statements regarding Critical Path Method (CPM) networks is true? A) There can be multiple critical paths on the same project, all with different durations. B) The early finish of an activity is the latest early start of all preceding activities. C) The late start of an activity is its late finish plus its duration. D) If a specific project has multiple critical paths, all of them will not have the same duration. E) B) and...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT