Question

Flex Inc., an electronic system integrator, developed a new product, which consists of a key component...

Flex Inc., an electronic system integrator, developed a new product, which consists of a key component sourced from a supplier and the software developed in house. For the coming selling season, Flex’s demand forecast for the integrated system is normally distributed with a mean of 1000 and standard deviation of 600. Flex incurs no costs associated with software integration. It sells the integrated system at $121 per unit to several of its key customers. Flex can also dump any integrated systems in a secondary electronic market for $50 per unit.

Flex can buy the key component from Solectric at $72 per unit. However, due to long lead time and short product life cycle, Flex has only one opportunity to place order with Solectric prior to the beginning of its selling season.

Another company, XE, can also supply the key component to Flex for $83.5 per unit. XE’s main value proposition is that it offers one-day delivery on any order no matter when the orders are submitted. Since the software integration can be done in one day and Flex promises one-week of lead time for its customers, the one-day lead time from XE will allow Flex to operate with make-to-order production system (i.e., Flex can take customer order first, then order from XE).

9.    If Flex sources exclusively from Solectric, what is the optimal order quantity?

10. If Flex decide to source from Solectric first, then from XE if the demand surpass the supply from Solectric, how should Flex place its order with both suppliers?          

Homework Answers

Answer #1

9)

Underage or shortage cost, Cu = 121 - 72 = 49

Overage or excess cost, Co = 72-50 = 22

Critical fractile = Cu/(Cu+Co) = 49/(49+22) = 0.6901

z = NORMSINV(0.6901) = 0.49625

Optimal order quantity to buy from Solectric = mean demand + z * std dev of demand

= 1000 + 0.49625*600

= 1298

10)

Underage or shortage cost, Cu = 83.5 - 72 = 11.5

Overage or excess cost, Co = 72-50 = 22

Critical fractile = Cu/(Cu+Co) = 11.5/(11.5+22) = 0.3433

z = NORMSINV(0.3433) = -0.4035

Optimal order quantity to buy from Solectric = mean demand + z * std dev of demand

= 1000 - 0.4035*600

= 758

For z=-0.4035, L(z) = 0.6327 (taken from standard normal loss table)

Expected shortage, L = std dev of demand * L(z) = 600*0.6327 = 380

Optimal order quantity to buy from XE = 380

Flex should buy 758 from Solectric and 380 from XE

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The specifications on an electronic component in a target-acquisition system are that its life must be...
The specifications on an electronic component in a target-acquisition system are that its life must be greater than 5000 hrs. Assume the life is normally distributed with mean 7500 hrs. The manufacturer realizes a sale price of $10 per unit produced (i.e. profit is $10 minus manufacturing cost); however, defective units must be replaced at a cost of $5 to the manufacturer, thus the defective cost will be $5 plus manufacturing cost. Two different manufacturing processes can be used, both...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes a printed circuit...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes a printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is...
Consider the problem statement for an "Online Auction System" to be developed: New users can register...
Consider the problem statement for an "Online Auction System" to be developed: New users can register to the system through an online process. By registering a user agrees to abide by different pre-defined terms and conditions as specified by the system. Any registered user can access the different features of the system authorized to him / her, after he authenticates himself through the login screen. An authenticated user can put items in the system for auction. Authenticated users can place...
A newly developed hospital requires an Electronic Decision Support System (DSS) for clinicians. This DSS is...
A newly developed hospital requires an Electronic Decision Support System (DSS) for clinicians. This DSS is required to have all the necessary features to help the practice. Develop a Software Requirements Specification (SRS) document that identifies all the necessary requirements for the system. This document must strictly follow the IEEE template uploaded on canvas. However, there may be sections in the template that may not apply to the project, these sections can be eliminated. Use the template below to answer...
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly,...
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed, the operator...
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly,...
Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 45 printed circuit boards. Each board requires 5 minutes of board assembly time. After each batch is completed, the operator...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in its manufacturing operation from a variety of different suppliers. One particular supplier provides a part where the assumptions of the EOQ model are realistic. The annual demand is 2,500 units, the ordering cost is $40 per order, and the annual holding cost rate is 25%. (a) If the cost of the part is $20 per unit, what is the economic order quantity? (b) Assume...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC)...
Lead Time Sound Tek Inc. manufactures electronic stereo equipment. The manufacturing process includes printed circuit (PC) board assembly, final assembly, testing, and shipping. In the PC board assembly operation, a number of individuals are responsible for assembling electronic components into printed circuit boards. Each operator is responsible for soldering components according to a given set of instructions. Operators work on batches of 50 printed circuit boards. Each board requires 4 minutes of board assembly time. After each batch is completed,...
1. If a company’s manufacturing cycle efficiency (MCE) is calculated as 0.6, then: a) 60% of...
1. If a company’s manufacturing cycle efficiency (MCE) is calculated as 0.6, then: a) 60% of the time a unit is in process is spent on activities that add value to the product. b) 40% of the time a unit is in process is spent on activities that add value to the product c) the largest component of the cycle is inspection time. d) there has been a calculation error. 2. Which of the following is correct regarding companies with...
FindMe Inc., (FI) has developed a coin-sized tracking tag that attaches to key rings, wallets, and...
FindMe Inc., (FI) has developed a coin-sized tracking tag that attaches to key rings, wallets, and other items and can be prompted to emit a signal using a smartphone app. FI sells these tags, as well as water-resistant cases for the tags, with terms FOB shipping point. Assume FI has no inventory at the beginning of the month, and it has outsourced the production of its tags and cases. FI uses FIFO and has entered into the following transactions: Jan....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT