Question

Problem 2-7 The following table shows data on the average number of customers processed by several...

Problem 2-7

The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $15, the overhead rate is 1.2 times labor cost, and material cost is $5 per customer.

Unit Employees Customers Processed / Day
A 5 38
B 6 44
C 5 56
D 3 31


a. Compute the labor productivity and the multifactor productivity for each unit. Use an eight-hour day for multifactor productivity.(Round your "Labor Productivity" answers to 1 decimal place and "Multifactor Productivity" answers to 3 decimal places.)

Unit Labor Productivity
(customers per day per worker)
Multifactor Productivity
(customers per dollar input)
A
B
C
D


b. Suppose a new, more standardized procedure is to be introduced that will enable each employee to process one additional customer per day. Compute the expected labor and multifactor productivity rates for each unit. (Round your "Labor Productivity" answers to 1 decimal place and "Multifactor Productivity" answers to 3 decimal places.)

Unit Labor Productivity
(customers per day per worker)
Multifactor Productivity
(customers per dollar input)
A
B
C
D

Homework Answers

Answer #1

Solution:

Hourly wage rate = $15

Labor cost = Hourly wage rate x Number of hours x Number of employees = $15 x 8 x Number of employees

Labor cost = $120 x Number of employees

Overhead rate = 1.2 x labor cost

Material cost = $5 per customer = $5 x Number of customers

(a) Labor productivity and Multifactor productivity:

Labor productivity = Number of customers / Number of employees

Multifactor productivity = Number of customers / Total cost

Total cost = Labor cost + Overhead cost + Material cost

The labor productivity and multifactor productivity for the given set of data is computed in the table below.

The calculated values are summarized in the table below:

(b) Revised Labor productivity and Multifactor productivity:

With new standardised procedure, each employee is able to process one additional customer per day. The revised labor productivity and multifactor productivity for the given set of data is computed in the table below.

The calculated values are summarized in the table below:

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following table shows data on the average number of customers processed by several bank service...
The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $15, the overhead rate is 1.0 times labor cost, and material cost is $5 per customer.     Unit Employees   Customers Processed / Day A 5 28 B 6 44 C 7 54 D 3 22     a. Compute the labor productivity and the multifactor productivity for each unit. Use an eight-hour day for multifactor productivity. (Round...
The following table shows data on the average number of customers processed by several bank service...
The following table shows data on the average number of customers processed by several bank service units each day. The hourly wage rate is $15, the overhead rate is 1.0 times labor cost, and material cost is $5 per customer.     Unit Employees   Customers Processed / Day A 5 28 B 6 44 C 7 54 D 3 22     a. Compute the labor productivity and the multifactor productivity for each unit. Use an eight-hour day for multifactor productivity. (Round...
Problem 10-11 (Algo) Direct Materials and Direct Labor Variances; Computations from Incomplete Data [LO10-1, LO10-2] Sharp...
Problem 10-11 (Algo) Direct Materials and Direct Labor Variances; Computations from Incomplete Data [LO10-1, LO10-2] Sharp Company manufactures a product for which the following standards have been set: Standard Quantity or Hours Standard Price or Rate Standard Cost Direct materials 3 feet $ 5 per foot $ 15 Direct labor ? hours ? per hour ? During March, the company purchased direct materials at a cost of $49,170, all of which were used in the production of 2,750 units of...
2. The following table contains data about the inventory for five items at Jones Corporation. Complete...
2. The following table contains data about the inventory for five items at Jones Corporation. Complete the missing items in the table. ITEM # BEGINNING UNIT INVENTORY ENDING UNIT INVENTORY AVERAGE UNIT INVENTORY ANNUAL UNIT SALES INVENTIORY TURNOVER 1 150,000 120,000 400,000 2 40,000 60,000 80,000 3 85,000 97,000 190,000 4 200,000 170,000 350,000 5 50,000 60,000 165,00 TOTAL   3. Suppose Jones Corporation in the above problem determined that its annual inventory carry cost = 18 percent. The item unit...
2.15 A silver dollar is flipped twice. Calculate the probability of each of the following occurring:...
2.15 A silver dollar is flipped twice. Calculate the probability of each of the following occurring: a)   A head on the first flip b)   A tail on the second flip given that the first toss was a head c)   Two tails d)   A tail on the first and a head on the second e)   A tail on the first and a head on the second or a head on the first and a tail on the second f)   At least...
Suppose that the table below shows an economy’s relationship between real output and the inputs needed...
Suppose that the table below shows an economy’s relationship between real output and the inputs needed to produce that output: Input Quantity Real GDP 300.00 $400 225.00   300 150.00   200 Instructions: Round your answers to 2 decimal places. a. What is the level of productivity in this economy? . b. What is the per-unit cost of production if the price of each input unit is $4? $. c. Assume that the input price increases from $4 to $5 with no...
Question 1 Based on the following data, calculate the single-factor productivity ratio using hours of labor...
Question 1 Based on the following data, calculate the single-factor productivity ratio using hours of labor for a housekeeping department. •   Number of employees = 100 •   Average hourly rate = $5.50 •   Total hours worked in September = 15,570 •   Total square feet maintained = 190,000 ANSWER Productivity = Output / Input Here, Output = total square feet maintained = 190,000 And, Input = total hours worked = 15,570 So, productivity will be 190,000 / 15,570 = 12.2 square...
Suppose that Hopeland and Faithland have the output figures contained in the below table, shown in...
Suppose that Hopeland and Faithland have the output figures contained in the below table, shown in terms of productivity per worker.    AVERAGE PRODUCT PER WORKER   Country Wheat Wine   Hopeland 3 bushels or 1 barrels   Faithland 1 bushel or 2 barrels        a. Assume that the costs and productivity remain constant. What is the opportunity cost of producing wheat and wine in Hopeland and Faithland?      Instructions: Round your answers to 2 decimal places. Hopeland Faithland   1 wheat = __________ wine...
The Bijou Theater shows vintage movies. Customers arrive at the theater line at the rate of...
The Bijou Theater shows vintage movies. Customers arrive at the theater line at the rate of 70 per hour. The ticket seller averages 45 seconds per customer, which includes placing validation stamps on customers’ parking lot receipts and punching their frequent watcher cards. (Because of these added services, many customers don’t get in until after the feature has started.) (Use the Excel spreadsheet Queue Models.) a. What is the average customer time in the system? (Round your answer to 2...
The frequency distribution shown in the following table lists the number of hours per day a...
The frequency distribution shown in the following table lists the number of hours per day a randomly selected sample of teenagers spent watching television. Where possible, determine what percent of the teenagers spent the following number of hours watching television. (Round your answers to one decimal place. If not possible, enter IMPOSSIBLE.) Hours per day Number of Teenagers 0 ≤ x < 1 19 1 ≤ x < 2 31 2 ≤ x < 3 23 3 ≤ x <...