Four Step Process with Rework and Scrap
Consider the following four step assembly operation with quality problems. All resources are staffed with one operator.
-The first resource has a processing time of 4 minutes per unit
-The second resource has a processing time of 3 minutes per unit. This process suffers from a high yield loss and 50% of all products have to be scrapped after this step.
-The third resource also suffers from quality problems. However, instead of scrapping the product, the third resource reworks it. The processing time at the third resource is 5 minutes per unit. In the 30% of the products in which the product needs to be reworked, this extends to a total (initial processing time plus rework) processing time of 10 minutes per unit. Rework always leads to a non-defective unit.
-No quality problems exist at the first and final resource. The processing time is 2 minutes per unit.
For every unit of demand, how many units have to flow through the third step in the process?
Where in the process is the bottleneck?
What is the process capacity?
Answer:
Step 1:
Step 2:
Step 3:
Step 4:
Hence the bottle neck is step 3, cycle time of the process is 6.5 mins, process capacity = 9.23 unit / hour
2 units are required for 1 unit output