Question

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...

The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:

Processing Due

Job Time (days) Date (Days)
W 4 4
X 3 5
Y 2 2
Z 1 1
If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today?
A.
0

B.
1

C.
2

D.
3

E.
4

Homework Answers

Answer #1

Answer: C-2

Explanation:

Job are sequenced according to SPT-Shortest processing time

Job

Duration

Due date

In flow time

Out Flow time

Z

1

1

0

1

Y

2

2

1

3

X

3

3

3

6

W

4

4

6

10

total

20

Average no. of Jobs per day= (sum job flow times)/ No. days to complete batch

                           = (20)/10 = 2 job

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown...
The owner/operator of the local franchise of Handyman, Inc. has 4 jobs to complete today, shown in the order in which they were received. Job Processing Time (hrs) Due (hrs from now) W 4 4 X 3 5 Y 2 2 Z 1 1 If he or she uses the earliest due date first priority rule to schedule these jobs, what will be the average tardiness?
You have the following information on four jobs. Today is the beginning of day 1, so...
You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining. Job Time Needed (days) Due (days) P 8 8 Q 10 23 R 3 17 S 6 30 T 4 29 U 7 24 1. If you order these jobs by Shortest Process Time rule, the order will be: 2. If you order these jobs by Earliest Due...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Assume that you are nearing graduation and have applied for a job with a local bank....
Assume that you are nearing graduation and have applied for a job with a local bank. As part of the bank’s evaluation process, you have been asked to take an examination that covers several financial analysis techniques. The first section of the test addresses discounted cash flow analysis. See how you would do by answering the following questions. a. Draw time lines for (1) a $100 lump sum cash flow at the end of Year 2, (2) an ordinary annuity...