Question

Product A is made from components B and C. Item​ B, in​ turn, is made from...

Product A is made from components B and C. Item​ B, in​ turn, is made from D and E. Item C also is an intermediate​ item, made from F and H.​ Finally, intermediate item E is made from H and G. Note that item H has two parents. The following are item lead​ times:

Item

A

B

C

D

E

F

G

H

Lead Time​ (weeks)

1

1

2

2

6

4

4

6

a. What lead time​ (in weeks) is needed to respond to a customer order for product​ A, assuming no existing inventories or scheduled​ receipts?

____ weeks.

b. What is the customer response time if all purchased items​ (i.e., D,​ F, G, and​ H) are in​ inventory?

____ weeks.

c. If you are allowed to keep just one purchased item in​ stock, which one would you​ choose?

Item B

Item H

Item E

Item C

Item F

Item D

Item G

Homework Answers

Answer #1
BOM path Total lead time= sum of all lead times in a path
ABD 4
ABEH 14
ABEG 12
ACF 7
ACH 9

a. The lead time​ (in weeks) is needed to respond to customer orders for product​ A, assuming no existing inventories or scheduled​ receipts

14 weeks. (Longest BOM path length)

b. if all purchased items​(i.e., D,​ F, G, and​ H) are in​ inventory

BOM path Total lead time= sum of all lead times in a path
ABD 2
ABEH 8
ABEG 6
ACF 3
ACH 3

8 weeks (Longest BOM path length)

c. Longest BOM length is 8 weeks, And H has the highest lead time therefore, I would keep H in stock.

Item H

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Product A is assembled from 6 components. The components are B, C, D, E, F, G....
Product A is assembled from 6 components. The components are B, C, D, E, F, G. Components B, D, and F are purchased from a supplier, complete and ready to assemble. Component C is assembled from parts H, I, and J. Component E is assembled from parts K and L. Component G is made in the plant from raw materials. Part H is made from parts M and N. Part L is made from parts P, Q, and R. Part...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the...
Question 18 Product D has gross requirements, on-hand inventory, and scheduled receipts as indicated in the time-phased inventory status record below. Its lead time is 3 weeks. Item D 1 2 3 4 5 6 Gross Requirements 100 300 100 400 100 50 On Hand/ Scheduled Receipts 700 Net Requirements A Planned Order Releases B The value of entry A is: A. 100 B. 200 C. 300 D. 700 E. None of the above. Reset Selection Question 19 Product D...
Product Y is made from one component P, three components Q, and one 2 components R.  P...
Product Y is made from one component P, three components Q, and one 2 components R.  P is made from two parts S, Q is made from one S, and R is made from two part S and three part T.  Other data includes: Part                 Lead time             Lot size                   On hand                 Scheduled receipts         Safety Stock Y                         1                                 lot-for-lot               30                                              none                                          5 P                        2                                   40                              15                                              none                                          none Q                        2                                 100                               8                                               none                                          8 R                        3                                 120                             30                                              none                                          none S                         2                                 500                             20                                              500, week 1                          20 T                         2                                 600                           370                                             none                                          50 a.    Draw the BOM for product Y. b. Complete the MRP explosion for product Y.  Identify any problems, and discuss possible solutions Master Production Schedule Finished...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item lead time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 12 B(2), J(3) C 4 15 G(2), B(2) K 4 21 H(4), B(2) B 3 32 J 4 27 G 4 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
The following table lists the components needed to assemble an end item, lead times (in weeks),...
The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 2 0 L(2), C(1), K(3) L 2 8 B(2), J(3) C 3 12 G(2), B(2) K 3 17 H(4), B(2) B 2 32 J 3 27 G 3 5 H 3 0 a. If 43 units of the end item are to be assembled, how many additional units of B are...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times...
Problem 12-3 The following table lists the components needed to assemble an end item, lead times (in weeks), and quantities on hand. Item Lead Time Amount on Hand Direct Components End 3 0 L(2), C(1), K(3) L 3 9 B(2), J(3) C 4 14 G(2), B(2) K 4 19 H(4), B(2) B 3 27 J 4 32 G 4 5 H 2 0 a. If 43 units of the end item are to be assembled, how many additional units of...
The following table lists the components used in assembling item FG-A. The following information is also...
The following table lists the components used in assembling item FG-A. The following information is also included for each component: lead time, the on-hand supply, and direct components. Item Lead Time (days) Available Inventory Direct Components FG-A 1 0 SA-B(1), SA-C (2), SA-D(2) SA-B 1 0 SA-D(2) SA-C 2 0 E (1), F(2) SA-D 2 0 E(3) E 1 10 --- F 3 5 --- Construct a product structure tree at a lowest level coding. Prepare a time-phased product structure....
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-C-D-F-G A-C-D-E-G A-B-E-G A-B-D-F-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity  ...
The activities described by the following table are given for the Howard Corporation in​ Kansas: Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s)   Activity   Time (in weeks)   Immediate Predecessor(s) A 10 - D 6 B G 6 E, F B 6 A E 10   B H 6 D C 3 A F 10 C I 2 G, H b) The activities on the critical path are
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT