ACTIVITY |
DESCRIPTION |
ACTIVITY PREDECESSOR |
A |
Legal and regulatory Authority |
- |
B |
Site Solicitation |
A |
C |
Site Selection and Preparation |
B |
D |
Drilling, Engineering and other Works |
B, C |
E |
Installation of other Equipment, Testing, and Analysis |
D |
F |
Project Commission and Handing over to the community |
E |
G |
Demonstrate safety usage and practices |
E, F |
H |
Preclosure safety analysis |
F, G |
1. create an activity precedence diagram showing the network
logic for each project activity you have identified;
2. prepare an activity duration table showing
optimistic, likely, and pessimistic activity times for each task;
and
3. create both the network diagram and Gantt
charts for your project, indicating the critical path, and all
critical activities, total project duration, and all activities
with float.