Question

Regarding line balancing, which of the following is correct? A. to meet demand, the actual cycle...

Regarding line balancing, which of the following is correct?

A. to meet demand, the actual cycle time should be no larger than the workstation cycle time;

B. The balanced line uses at most the theoretic minimum number of workstations

C. the lower the efficiency, the better the line

D. All of the above statements are wrong.

Homework Answers

Answer #1

To meet demnd the actual cycle time depends on the demand and total time available. It can be larger than workstation cycle time.

If the number of workstations is greater than the theoretic minimum number of workstations, still th eline ill remain balanced, hower efficiency will reduce. Hence, actual number of workstations may be greater than the theoretic minimum number of workstations.

The line becomes better with increased efficiency, since cycle time decreases and productivity improves.

Hence, all statements given as options A,B and C are wrong.

Correct option is (D)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 100 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
There are seven tasks in an assembly line, from which a product with a relative stable...
There are seven tasks in an assembly line, from which a product with a relative stable demand is produced. The time needed for each task (in minutes) and the relationships among tasks are in the graph below (note that activity C is linked to activity D). The assembly line operates 8 hours a day. The daily customer demand for the product is 120 units. Please design/balance this assembly line, so that supply and demand would be matched the most efficiently...
Line balancing: With considering the following tasks: task number avg. performance time number of successors 1...
Line balancing: With considering the following tasks: task number avg. performance time number of successors 1 5 7 2 3 6 3 6 4 4 8 5 5 10 3 6 7 3 7 1 2 8 5 0 9 3 0    a. Estimate the cycle time to reach minimum idle time and end up having 4 workstations.   b. Imagine the considered cycle time is 17. Which of the following methods gives us the best solution? Why? (you need...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per...
Wild Widget must set up an assembly line for widgets. Forecasts show that 52 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: Task Time (seconds) Predecessors A 10 – B 33 A C 23 A D 24 C,B E 20 D F 18 D G 36 E,F b. What is the takt time? (Round your answer to the nearest whole number.) c. What is the theoretical number of workstations? (Round up...
Which of the following statements ARE correct, regarding the situation if you are in a elevator,...
Which of the following statements ARE correct, regarding the situation if you are in a elevator, standing on a scale? Group of answer choices when you go up with increasing speed, the scale should give your a number greater than you actual weight when you go down with slowing down speed, the scale should give your a number less than you actual weight when you go up with slowing down speed, the scale should give your a number greater than...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar...
Fine’s Furniture is known for its fine cedar chests. The tasks necessary to assemble the cedar chests, the length of time needed to perform each task, and the operations that must be complete prior to subsequent operations are given below. With a production quota of 300 units in a 35 hour week, the desired cycle time is closest to ______. Element Time (min) Predecessors A 2 NONE B 3 A C 5 B D 5 NONE E 4 D F...
1)What is the outcome when a bottleneck resource is augmented with more capacity? Throughput time increases...
1)What is the outcome when a bottleneck resource is augmented with more capacity? Throughput time increases Cycle time decreases The resource with the second least utilization becomes the bottleneck All of the above 2)Which of the following statements are true? Installed capacity in service systems are always based on peak demand Service systems designed to handle average capacity will be more effective Improving effectiveness of a service will require greater investment of capacity None of the above 3)The arrival rate...
Which of the following statements is NOT correct?           a.       The poverty line (or poverty threshold)...
Which of the following statements is NOT correct?           a.       The poverty line (or poverty threshold) here in the United States is approximately three times the amount needed to purchase an adequate diet.           b.       The poverty line (or poverty threshold) here in the United States is about $26,000 per year for a family of four.           c.       Someone who works full-time for eight dollars per hour (-just above the minimum wage-) will work approximately 2,000 hours over an entire...
1 Which of the following statements is TRUE regarding time series forecasting methods? a Moving average...
1 Which of the following statements is TRUE regarding time series forecasting methods? a Moving average (MA) method is appropriate for forecasting an item that shows seasonal pattern b By assigning larger weight to the most recent period data, weighted moving average (WMA) method is more reflective to the changes in the most recent period of data than MA method c Simple exponential smoothing method is NOT appropriate for forecasting stable item without trend d Linear trend line method is...
1. If a company’s manufacturing cycle efficiency (MCE) is calculated as 0.6, then: a) 60% of...
1. If a company’s manufacturing cycle efficiency (MCE) is calculated as 0.6, then: a) 60% of the time a unit is in process is spent on activities that add value to the product. b) 40% of the time a unit is in process is spent on activities that add value to the product c) the largest component of the cycle is inspection time. d) there has been a calculation error. 2. Which of the following is correct regarding companies with...