Question

Explain how schedule management is different when using an agile project management approach compared to traditional...

  1. Explain how schedule management is different when using an agile project management approach compared to traditional planbased project management.                                                                                                      

  1. In Scrum,why is it useful to hold retrospectives at the end of weekly iterations?

(1 mark)

Homework Answers

Answer #1

Schedule management is a list of project-related activities and project deliverables where the starts and the finish dates as well as the duration of the activities are scheduled. Schedule management contributes much to time management. In the agile schedule management, the project activities are break down into smaller section and they are released for testing and quality assurance. On the other hand, traditional project schedule management is where the project is run in a sequential cycle.

Hope this helps :)

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. What is an iteration from the agile approach and how does it compare to phases...
1. What is an iteration from the agile approach and how does it compare to phases from the traditional software development life cycle? 2. What is team velocity and how does it impact the development of a project? 3. What is the purpose of SCRUM meetings, and how can one best prepare to take part in it? I would like a very detailed answer, I need to understand the concept of agile very well.
Will extinction be any different when the behavior is previously reinforced on an intermittent schedule, compared...
Will extinction be any different when the behavior is previously reinforced on an intermittent schedule, compared to a continuous schedule (CRF)? Why or why not?
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Reaching an agreement on a set of requirements is very critical for any software project. This...
Reaching an agreement on a set of requirements is very critical for any software project. This set of approved requirements is called the requirements baseline. In 1–2 paragraphs, explain what you need to go through until you can baseline a set of requirements and how can you do this baselining for agile projects. Include the following in your answer: The different stakeholders that need to be involved Customers or end users Developers Testers Management The main considerations for these different...
You have proposed a hybrid approach to delivering a program. It has one project that blends...
You have proposed a hybrid approach to delivering a program. It has one project that blends PRINCE2, Lean & Six Sigma, and another project using SCRUM. There are also some linear elements to some of the projects within your program. Your program sponsor says she hates the idea of doing anything other than very traditional approaches and does not want to mix things up. She says it will be too confusing and it just sounds like you are trying to...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance...
Part 1 a) Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original...
Fundamentals of Project Management Research a real world example of a project. Based on your research...
Fundamentals of Project Management Research a real world example of a project. Based on your research and the identified project, answer the following questions: What project have you selected? Explain. Provide reasons for selecting the project. What kind of organization or industry does your selected project belongs to? How does the project you selected fit the definition of a project? Is your selected project constrained by performance, cost, or schedule? Why or why not? To what extent, does the project...
Discuss how project or team management is distinct. What areas are different and why?
Discuss how project or team management is distinct. What areas are different and why?
Discuss how project or team management is distinct. What areas are different and why?
Discuss how project or team management is distinct. What areas are different and why?