Question

Question 2                                        &nbsp

Question 2                                                       [13 Marks]

Activity

Original Duration (in Months)

Crash Duration (in Months)

Time Savings

Original Cost in Dollars

Crash Cost

Extra Cost

Cost per Month

F

14

12

2

10,000

14,000

4,000

2,000

A

9

8

1

17,000

27,000

10,000

10,000

H

3

2

1

25,000

26,000

1,000

1,000

G

7

5

2

10,000

16,000

6,000

3,000

C

11

8

3

27,000

36,000

9,000

3,000

  1. Imagine that this project has a project float of -3 (minus three) months. Which activity or activities presented above would you crash to save three months on the project, assuming that the activities listed above represent critical path activities?
  1. How much would it cost to crash this project?

Homework Answers

Answer #1

Crash H is by 1 month

Crash F is by 2 months

GIven the float is -3, the project has to be crashed by 3 months to bring it back on track.

Therefore , first crash H by 1 month since it has the least extra cost per month of $1,000.

The maximum time saving for H was 1 month.

So, next move on to the activity F for it has the next least extra cost per month of $2,000.

Crash F by 2 months which was the maximum time-saving.

Total cost of crashing = 1 month of H * $1,000/ month + 2 months of F * $2,000/ month = $5,000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
Question 1. What is the INTERNAL RATE OF RETURN for project A? (Assume a discount rate...
Question 1. What is the INTERNAL RATE OF RETURN for project A? (Assume a discount rate of 8%) Year Project A Project Z 0 -$35,000 -$350,000 1 17,000 110,000 2 17,000 110,000 3 16,000 105,000 4 15,000 100,000 5 14,000 100,000 36.74% 32.24% 28.71% 22.65% Question 2. What is the PROFITABILITY INDEX for project A? (Assume a discount rate of 8%) Year Project A Project Z 0 -$35,000 -$350,000 1 17,000 110,000 2 17,000 110,000 3 16,000 105,000 4 15,000...
Below are the project steps for the creation of a television advertisement for Foolio, which is...
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created.    Consider the following data for questions 1 through 5: Activity Duration (days) Description Preceding Activity(ies) A 6 Create script for advertisement - B 4 Book technical crew A C 4 Book actors A D 3 Create props and costumes B,C E 6 Book location C F 5 Filming and editing D,E How many paths...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost...
Use the following data for question below. Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Pred 1 Pred 2 A 10 7 $200 $400 B 15 10 $250 $600 C 13 8 $600 $1,500 A B D 14 10 $800 $1,200 A B E 8 4 $1,000 $3,000 C D F 12 6 $1,200 $1,800 C D G 7 6 $700 $1,400 E F H 5 3 $500 $900 E F If the project must...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
Use the following activities and their three duration estimates (in days) to do the following Determine...
Use the following activities and their three duration estimates (in days) to do the following Determine the expected duration of the project – use 2 decimals when determining the duratio Path Activity Optimistic Most Likely Pessimistic a-b-c A 4 5 6 B 7 8 10 C 3 5 9 d-e-f D 7 8 11 E 2 3 4 f 1 4 6
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...
The university IT team is working on the implementation of a new software system for enrollment.  Using...
The university IT team is working on the implementation of a new software system for enrollment.  Using the following table, complete the requested tasks: Activity Immediate Predecessor Normal Crash Normal Crash A - 6 5 $900 $1,000 B A 8 6 $300 $400 C A 4 3 $500 $600 D B 5 3 $900 $1,200 E C, D 8 5 $1,000 $1,600 a. Draw the network diagram noting normal and crash times. b. What is the critical path? c. What is...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...