Five jobs arrived to be processed with the processing times and due dates.

Present Date=

300

Work Order

A

B

C

D

E

Processing Times (Days)

14

5

40

12

7

Due Date

167

163

195

191

161

. . .

Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the LIFO schedule is “EDCBA” (where job “E” is the first job).

Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct?     (A) 0   (B) 1   (C) 2   (D) 3   (E) 4

The schedule based on the MPT sequencing rule is BEDAC

The schedule based on the EDD sequencing rule is BAEDC

The schedule based on the MST sequencing rule is AEBCD

The schedule based on the MCR sequencing rule is BEADC

. . .

Question 4.   Consider the MPT schedule.

How many statements are correct?   (A) 0   (B) 1   (C) 2   (D) 3   (E) 4

Statement 1. The total processing time of the schedule is 157

Statement 2. The total flow of the schedule is 78

Statement 3. The total lateness of the schedule is 157

Statement 4. The Makespan of the schedule is 78

. . .

Question 5.   Consider the FIFO schedule.

How many statements are correct?   (A) 0   (B) 1   (C) 2   (D) 3   (E) 4

Statement 1. The flow of job B is 5

Statement 2. The lateness of job C is 164

Statement 3. The date of completion of job D is 180

Statement 4. The queue time of job E is 78

. . .

Homework Answers

Answer #1

Compute Slack Time and Critical Ratio for each job as under:

Slack Time = Due Date - Processing Time

Critical Ratio = Due Date / Processing Time

Work Order A B C D E
Processing Times (Days) 14 5 40 12 7
Due Date 167 163 195 191 161
Slack Time 153 158 155 179 154
Critical Ratio 11.92857 32.6 4.875 15.91667 23

Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the LIFO schedule is “EDCBA” (where job “E” is the first job).

Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct?     (A) 0   (B) 1 (C) 2   (D) 3   (E) 4

The schedule based on the MPT sequencing rule is BEDAC

The schedule based on the EDD sequencing rule is BAEDC

The schedule based on the MST sequencing rule is AEBCD

The schedule based on the MCR sequencing rule is BEADC

. . .

Using MPT rule, jobs are scheduled as per ascending order of their Processing Time. So, the given schedule, i.e.  BEDAC is correct.

Using EDD rule, jobs are scheduled as per ascending order of their Due Date. So, the given schedule, i.e. BAEDC is incorrect. The correct schedule is EBADC

Using MST rule, jobs are scheduled as per ascending order of their Slack Time. So, the given schedule, i.e. AEBCD is incorrect. The correct schedule is AECBD

Using MCR rule, jobs are scheduled as per ascending order of their Critical Ratio. So, the given schedule, i.e. BEADC is incorrect. The correct schedule is CADEB

Therefore, only 1 schedule is correct, i.e. MPT

ANSWER: (B) 1

. . .

Question 4.   Consider the MPT schedule.

How many statements are correct?   (A) 0   (B) 1   (C) 2   (D) 3   (E) 4

Statement 1. The total processing time of the schedule is 157

Statement 2. The total flow of the schedule is 78

Statement 3. The total lateness of the schedule is 157

Statement 4. The Makespan of the schedule is 78

. . .

MPT schedule is following:

Work Order Processing Times (Days) Due Date Flow Time = Running sum of processing time Completion time = 300 + Flow time Lateness = Completion time - Due Date
B 5 163 5 305 142
E 7 161 12 312 151
D 12 191 24 324 133
A 14 167 38 338 171
C 40 195 78 378 183
Total 78 157 780

Statement 1 is incorrect, because total processing time of the schedule is 78

Statement 2 is incorrect, because total flow time of the schedule is 157

Statement 3 is incorrect, because total lateness is 780 and average lateness = 780/5 = 156

Statement 4 is correct, as Makespan of the schedule = Sum of processing times of all jobs = 78

Therefore, only one statement is correct.

ANSWER: (B) 1

. . .

Question 5.   Consider the FIFO schedule.

How many statements are correct?   (A) 0   (B) 1 (C) 2   (D) 3   (E) 4

Statement 1. The flow of job B is 5

Statement 2. The lateness of job C is 164

Statement 3. The date of completion of job D is 180

Statement 4. The queue time of job E is 78

. . .

FIFO schedule is following:

Work Order Processing Times (Days) Due Date Flow Time Completion time Lateness Queue Time
A 14 167 14 314 147 0
B 5 163 19 319 156 14
C 40 195 59 359 164 19
D 12 191 71 371 180 59
E 7 161 78 378 217 71
Total 78 241 864 163

As we see in the above schedule, Only statement 2 is correct


ANSWER: (B) 1.

. . .

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E, arrived in that order to be processed on two machines. Job A B C D E Time on Machine 1 45 53 63 31 75 Time on Machine 2 42 65 61 53 77 Question 6. Which is the Johnson’s Rule schedule?      (A) ‘ACEBD’     (B) ‘DCABE’     (C) ‘DBECA’     (D) ‘DABEC’   (E) none...
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 5.   Questions 8,9. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd, for A,B,C, respectively.] Consider the jobs scheduled on two machines in the order of (A,B,C) where each job is started as soon as possible. The processing times for each job on each machine are given in the table below. Assume time on machine #1 is represented with “(1)” and on machine #2 with “(2)”. Job Machine#1 Time Machine#2 Time...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7...
The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7 16 3 2 8 4 6 21 5 3 9 If we are interested in Job Lateness as a measure, is SPT or FCFS the better sequencing method to use? If we are interested in Flow Time as a measure, is SPT or FCFS the better sequencing method to use?
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E,...
[Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E, arrived in that order to be processed on two machines. Job A B C D E Time on Machine 1 40 48 58 26 70 Time on Machine 2 37 60 56 48 72 Question 6. Which is the Johnson’s Rule schedule?      (A) ‘DBECA’     (B) ‘ACEBD’     (C) ‘DCABE’     (D) ‘DABEC’   (E) none of the above Question 7. Consider the FIFO schedule of (A,B,C,D,E)....
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT