Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ]
[Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.]
Five jobs arrived to be processed with the processing times and due dates.
Present Date= |
300 |
||||
Work Order |
A |
B |
C |
D |
E |
Processing Times (Days) |
14 |
5 |
40 |
12 |
7 |
Due Date |
167 |
163 |
195 |
191 |
161 |
. . .
Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the LIFO schedule is “EDCBA” (where job “E” is the first job). Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 The schedule based on the MPT sequencing rule is BEDAC The schedule based on the EDD sequencing rule is BAEDC The schedule based on the MST sequencing rule is AEBCD The schedule based on the MCR sequencing rule is BEADC . . . |
Question 4. Consider the MPT schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The total processing time of the schedule is 157 Statement 2. The total flow of the schedule is 78 Statement 3. The total lateness of the schedule is 157 Statement 4. The Makespan of the schedule is 78 . . . |
Question 5. Consider the FIFO schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The flow of job B is 5 Statement 2. The lateness of job C is 164 Statement 3. The date of completion of job D is 180 Statement 4. The queue time of job E is 78 . . . |
Compute Slack Time and Critical Ratio for each job as under:
Slack Time = Due Date - Processing Time
Critical Ratio = Due Date / Processing Time
Work Order | A | B | C | D | E |
Processing Times (Days) | 14 | 5 | 40 | 12 | 7 |
Due Date | 167 | 163 | 195 | 191 | 161 |
Slack Time | 153 | 158 | 155 | 179 | 154 |
Critical Ratio | 11.92857 | 32.6 | 4.875 | 15.91667 | 23 |
Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the LIFO schedule is “EDCBA” (where job “E” is the first job). Consider the schedules based on the sequencing rules: Minimum Processing Time (MPT); Earliest Due Date (EDD); Minimum Slack Time (MST); and Minimum Critical Ratio (MCR). How many of the schedules are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 The schedule based on the MPT sequencing rule is BEDAC The schedule based on the EDD sequencing rule is BAEDC The schedule based on the MST sequencing rule is AEBCD The schedule based on the MCR sequencing rule is BEADC . . . Using MPT rule, jobs are scheduled as per ascending order of their Processing Time. So, the given schedule, i.e. BEDAC is correct. Using EDD rule, jobs are scheduled as per ascending order of their Due Date. So, the given schedule, i.e. BAEDC is incorrect. The correct schedule is EBADC Using MST rule, jobs are scheduled as per ascending order of their Slack Time. So, the given schedule, i.e. AEBCD is incorrect. The correct schedule is AECBD Using MCR rule, jobs are scheduled as per ascending order of their Critical Ratio. So, the given schedule, i.e. BEADC is incorrect. The correct schedule is CADEB Therefore, only 1 schedule is correct, i.e. MPT ANSWER: (B) 1 . . . |
|||||||||||||||||||||||||||||||||||||||||||||||||
Question 4. Consider the MPT schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The total processing time of the schedule is 157 Statement 2. The total flow of the schedule is 78 Statement 3. The total lateness of the schedule is 157 Statement 4. The Makespan of the schedule is 78 . . . MPT schedule is following:
Statement 1 is incorrect, because total processing time of the schedule is 78 Statement 2 is incorrect, because total flow time of the schedule is 157 Statement 3 is incorrect, because total lateness is 780 and average lateness = 780/5 = 156 Statement 4 is correct, as Makespan of the schedule = Sum of processing times of all jobs = 78 Therefore, only one statement is correct. ANSWER: (B) 1 . . . |
|||||||||||||||||||||||||||||||||||||||||||||||||
Question 5. Consider the FIFO schedule. How many statements are correct? (A) 0 (B) 1 (C) 2 (D) 3 (E) 4 Statement 1. The flow of job B is 5 Statement 2. The lateness of job C is 164 Statement 3. The date of completion of job D is 180 Statement 4. The queue time of job E is 78 . . . FIFO schedule is following:
As we see in the above schedule, Only statement 2 is correct
. . . |