The Attaran Corporation manufactures two electrical products: portable air conditioners and portable heaters. The assembly process for each is similar in that both require a certain amount of wiring and drilling. Each air conditioner takes
3
hours of wiring and
2
hours of drilling. Each heater must go through
2
hours of wiring and
1
hour of drilling. During the next production period,
240
hours of wiring time are available and up to
140
hours of drilling time may be used. Each air conditioner sold yields a profit of
$20
Each heater assembled may be sold for a
$15
profit.
The optimum solution is:
Number of air conditioners to be produced =
0
(round your response to two decimal places).
Number of heaters to be produced =
nothing
(round your response to two decimal places).
The problem is linear programming problem with objective is to maximize profit:
Objective function : Maximize Z = 20X1 + 15X2
Here,
Subject to:
3X1 + 2X2 240 (Total wiring time available)
2X1 + 1X2 140 (Total drilling time available)
X1 and X2 0 (Non negativity)
The excel formulation is shown below:
The solver equations are shown below:
The solution is shown below:
The product mix is shown below:
The total profit is $1800