Question

Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

Consider the network described in the table below.

Activity

Immediate

Predecessor(s)

Pessimistic

Probable

Optimistic

J

--

15

10

8

K

--

9

8

7

L

J

10

6

5

M

J

3

3

3

N

K,M

9

5

1

O

K,M

10

7

4

P

L,N

10

8

3

a. Calculate the expected duration of each activity.

b. Calculate the expected duration and variance of the critical path.

c. Calculate the probability that the project will be completed in fewer than 30 time units.

d. What time corresponds to when the top 30% of those complete the project?

Homework Answers

Answer #1

a. Expected activity duration = pessimistic duraion + 4x probable duration + optimistic duration /6

Duration of J = 15+40+8/6 = 10.5

Duration of K =9+32+7 /6 =8

similarly the durations of activities

Activity duration
J 10.5
K 8
L 6.5
M 3
N 5
O 7
P 7.5

b.

Critical path is JMNP

Variance = ( optimistic time -pessimistic time/6)2

Variance of J = ( 15-8/6)2 = 1.36

Variance of M =0

Variance of N = (1-9/6)2 = 1.77

Variance of P = (3-10/6)2 = 1.36

Total variance of critical path = 1.36+0+1.77+1.36 =4.49

Standard deviation = ( variance)1/2 = 2.11

c.

Probability of completion of project before 30 time units

z = x-mean / sd

z =30-26/2.11 =1.89

which corresponds to 97.06% probability

d. Let this time be t

now z = t-26/2.11

z corresponding to 30% is -0.52

-0.52 = t-26 /2.11

which gives t = 24.9

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration...
Use the table below to answer the questions 25 to 28. Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U Calculate the actual duration of each activity (fill-in the table) Draw an AOA network diagram for the activities (in the space below):...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration...
Use the table below to answer the questions Activity Optimistic duration Pessimistic duration Most Likely duration Weighted duration Immediate Predecessor P 15 27 21 - Q 18 36 24 P R 26 40 24 P S 21 39 27 Q T 27 33 24 Q,R U 16 32 24 S,T V 16 30 26 U 1. Calculate the actual duration of each activity (fill-in the table) 2. Draw an AOA network diagram for the activities (in the space below): 3....
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8...
Fill out the charts with the correct information. Activity Optimistic Most Probable Pessimistic A 3 8 13 B 5 7 9 C 5 12 19 D 2 5 8 E 5 9 19 F 4 8 18 G 9 15 21 H 4 6 14 If required, round your answers to two decimal places. A.) Find the critical path. Activity Expected Time Variance A B C D E F G H Earliest Latest Earliest Latest Critical Activity Start Start Finish...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site...
ACTIVITY DESCRIPTION ACTIVITY PREDECESSOR A Legal and regulatory Authority - B Site Solicitation A C Site Selection and Preparation B D Drilling, Engineering and other Works B, C E Installation of other Equipment, Testing, and Analysis D F Project Commission and Handing over to the community E G Demonstrate safety usage and practices E, F H Preclosure safety analysis F, G 1. create an activity precedence diagram showing the network logic for each project activity you have identified; 2.    prepare...