Question

Why should project teams take the time to determine the critical path for a project?

Why should project teams take the time to determine the critical path for a project?

Homework Answers

Answer #1

It is very essential for a project team to take time to determine the critical path for a project as:

· It helps to know the project duration as project duration is equal to duration of critical path

· It helps to know the activities which are critical for project duration and team can work upon ways to cut down the timeline so that project can be completed early

· It helps to know the float for each activity which is the duration for which activity can be delayed without impacting project timeline

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. What is the critical path, and how long is the project expected to take?
1. What is the critical path, and how long is the project expected to take?
For the following network determine: a) The activities on the critical path b) The time for...
For the following network determine: a) The activities on the critical path b) The time for the critical path c) The slack for EVERY activity Activity Immediate Predecessors Time A - 5 B - 6 C A,B 7 D A,B 6 E A,B 8 F C,D,E 4 G C,D,E 3
The estimated time for the critical path is 44.5 weeks. ?The activity variance along the critical...
The estimated time for the critical path is 44.5 weeks. ?The activity variance along the critical path is 22.027 weeks. ?f) The probability that Hopkins Hospitality will finish the project in 40 weeks or less is ? ?(Enter as a probability and round your response to three decimal? places.)
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
Find the critical path and the project completion time for the following list of activities. Calculate...
Find the critical path and the project completion time for the following list of activities. Calculate the probabilities of completing the following project in: a) 13 days or more b) 11 days or less c) Between 12 and 14 days Activity Immediate Predecessor Optimistic Duration Most Probable Duration Pessimistic Duration A - 1 3 5 B - 2 4 6 C A,B 2 4 5 D A,B 3 5 7 E C,D 1 2 10 I do not understand how...
13. In critical path management, which is a general rule for crashing activities? A. Crash activities...
13. In critical path management, which is a general rule for crashing activities? A. Crash activities on the critical path B. Crash activities that are not on the critical path C. Crash activities having the greatest number of predecessor activities D. Crash activities having the greatest number of following activities E. Crash activities having the lowest crashing costs 14. Suppose a project has a crash time of 40 weeks. The normal cost of the project is $60,000, and the crash...
When activity times are known with certainty, the critical path is defined as the set of...
When activity times are known with certainty, the critical path is defined as the set of activities on a path from the project’s start event to its finish event that, if delayed, will delay the completion date of the project. Why must this definition be modified in situations where the activity times are not known with certainty? Are there dangers associated with not modifying the definition? (not more than 150 words).
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has...
Question: The project’s progress has fallen behind schedule on the critical path. The project manager has decided to recover the schedule by crashing the project’s schedule. What is the expected consequence of this project’s triple constraints?
The information for project X is shown below. What are the critical path and the completion...
The information for project X is shown below. What are the critical path and the completion time of the project? Crashing Costs Activity Preceding Normal Time 1st Week 2nd Week K — 8 weeks $4100 — L K 6 weeks 3250 — N K 1 week 450 450 M L 5 weeks 3000 3500 J N 4 weeks 500 — Q J,M 6 weeks 4000 4000 KLMQ, 25 weeks KLNMJQ: 25 weeks KNJQ, 25 weeks KNJQ, 30 weeks KLMQ, 30...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be...
Given the information below: (Use normal time to calculate original path) a) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 22 to 21 days? b) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 21 to 20 days? c) Which activity(s) should be crashed and what is the cost to reduce the project completion time from 20 to19 days? d) What is the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT