Question

please show work 11) Activity Predecessors Expected Duration (in minutes) Variance of Duration (in minutes) A...

please show work

11)

Activity

Predecessors

Expected Duration (in minutes)

Variance of Duration (in minutes)

A

----

10

1.2

B

A

5

1.00

C

A

15

2.4

D

B, C

11

1.5

E

D

10

1.8

a). For the above projects find the expected duration and standard deviation of the project duration. (6points)

b. Based on your calculations from part “a” what is the probability that the project will be completed in 50 minutes. (4points)

c. How many minutes will the project be completed, if the company projects 90% probability for completion. (5points)

Homework Answers

Answer #1

Answer a


Answer b


Answer c

Dear Student,
Please ask, if you have any doubts through the comment section. Do rate the answer.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are...
The estimated times and immediate predecessors for the activities in a project at Paccar Winch are given in the following table. Assume that the activity times are independent Activity Immediate Predecessor Time (Weeks) a m b A - 9 10 11 B - 4 10 16 C A 9 10 11 D B 5 8 11 a) Calculate the expected time and variance for each activity. b) What is the expected completion time of the critical path? What is the...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7...
Activity Depends on Optimistic Duration (Days) Most Likely Duration (days) Pessimistic Duration (Days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Refer to the information above: Determine the following for each activity: Expected Duration (round to the nearest...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is...
#3) Planned duration of a project is 28 weeks. Budget at completion for the project is $525,000. The project is in its 25th week. The actual cost (thus far) is $270,000. At this point in the plan, the planned cost was expected to be $261,000. For the work performed to date, the earned value is estimated at $272,000. Compute the following for the project (10 points) a) Cost variance. b) Schedule variance. c) If rest of the project is assumed...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the...
Given the following network and activity time estimates, determine earliest and latest activity times, slack, the expected project completion time and variance, and the probability that the project will be completed in 28 days or less. TIME ESTIMATES (DAYS) ACTIVITY ACTIVITY PREDECESSOR a m b A - 5  8 17 B - 7 10 13 C A 3  5  7 D A 1  3  5 E B, C 4  6  8 F B, C 3  3  3 G D,E 3  ...
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A -...
Refer to the information below: Depends On Optimistic Duration(days) Most Likely Duration(days) Pessimistic Duration(days) A - 7 10 18 B A 3 8 14 C B 10 14 22 D A 2 5 9 E B,D 7 9 15 F C,D 4 9 19 G B 10 15 29 H C,E,F 2 8 19 I G,H 1 2 7 J I 3 9 18 Determine the following for each activity: Expected Duration (round to the nearest whole number) Early Start...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A...
Activity Immediate Predecessor Optimistic Time Most-likely time Pessimistic Time A None 3 6 9 B A 3 5 7 C A 4 7 12 D B 4 8 10 E C 5 10 16 F D, E 3 4 5 G D, E 3 6 8 H F 5 6 10 I G 5 8 11 J H, I 3 3 3 (a). What is the expected time for each activity? (2 points) (b.) What is the variance for each...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...
Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K,M 9 5 1 O K,M 10 7 4 P L,N 10 8 3 a. Calculate the expected duration of each activity. b. Calculate the expected duration and variance of the critical path. c. Calculate the probability that the project will be completed in fewer...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...