please show work
11)
Activity |
Predecessors |
Expected Duration (in minutes) |
Variance of Duration (in minutes) |
A |
---- |
10 |
1.2 |
B |
A |
5 |
1.00 |
C |
A |
15 |
2.4 |
D |
B, C |
11 |
1.5 |
E |
D |
10 |
1.8 |
a). For the above projects find the expected duration and standard deviation of the project duration. (6points)
b. Based on your calculations from part “a” what is the probability that the project will be completed in 50 minutes. (4points)
c. How many minutes will the project be completed, if the company projects 90% probability for completion. (5points)
Answer a
Answer b
Dear Student,
Please ask, if you have any doubts through the comment section.
Do rate the answer.
Get Answers For Free
Most questions answered within 1 hours.