Question

Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...

Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table:

SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE
1 15 0
2 15 0
3 15 0
4 15 2
5 15 0
6 15 3
7 15 1
8 15 0
9 15 3
10 15 1
a.

Determine the p−p−, Sp, UCL and LCL for a p-chart of 95 percent confidence (1.96 standard deviations). (Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 3 decimal places.)

  p−p−   
  Sp   
  UCL   
  LCL   

Homework Answers

Answer #1

Solution:

Given,

Z = 1.96

Number of samples, N = 10

Number of parts in each sample, n = 15

(a) P = Total number of defective items in the sample / (Number of samples x Sample size)

P = (2 + 3 + 1 + 3 + 1) / (10 x 15)

P = 0.067

(b) Sp = SQRT [P x (1 - P)] / n

Sp = SQRT [0.067 x (1 - 0.067)] / 15

Sp = 0.065

(c) UCL = P + [Z x Sp]

UCL = 0.067 + [1.96 x 0.065]

UCL = 0.194

(d) LCL = P - [Z x Sp]

LCL = 0.067 - [1.96 x 0.065]

LCL = - 0.060 or 0 (Number of defects cannot be negative)

LCL = 0

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 0 2 15 2 3 15 0 4 15 3 5 15 1 6 15 3 7 15 1 8 15 0 9 15 0 10 15 0 a. Determine the p−p−, Sp, UCL and LCL...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 1 2 15 1 3 15 3 4 15 1 5 15 0 6 15 0 7 15 2 8 15 1 9 15 2 10 15 1 a. Determine the p−p− , Sp, UCL and...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart...
Ten samples of 15 parts each were taken from an ongoing process to establish a p-chart for control. The samples and the number of defectives in each are shown in the following table: SAMPLE n NUMBER OF DEFECTIVE ITEMS IN THE SAMPLE 1 15 2 2 15 2 3 15 2 4 15 0 5 15 2 6 15 1 7 15 3 8 15 2 9 15 1 10 15 3 a. Determine the p−p− , Sp, UCL and...
A process produces parts that are determined to be usable or unusable. The process average defective...
A process produces parts that are determined to be usable or unusable. The process average defective rate is 1%. You plan to monitor this process by taking samples of 400 parts. Sample: 1 2 3 4 5 6 7 8 9 10 Defectives: 6 2 5 6 0 4 8 0 2 8   (A.) What is your p chart UCL? (B.) What is your p chart LCL? (C.) Is this process in control or not?
Twelve​ samples, each containing five​ parts, were taken from a process that produces steel rods at...
Twelve​ samples, each containing five​ parts, were taken from a process that produces steel rods at Emmanual​ Kodzi's factory. The length of each rod in the samples was determined. The results were tabulated and sample means and ranges were computed. Refer to Table S6.1 - Factors for computing control chart limits (3 sigma) for this problem. Sample ​Size, n Mean​ Factor, A2 Upper​ Range, D4 Lower​ Range, D3 2 1.880 3.268 0 3 1.023 2.574 0 4 0.729 2.282 0...
A shirt manufacturer buys cloth by the 100 yard roll from a supplier. For setting up...
A shirt manufacturer buys cloth by the 100 yard roll from a supplier. For setting up a control chart to manage the irregularities (e.g., loose threads and tears) the following data was collected from a sample provided by the supplier. SAMPLE 1 2 3 4 5 6 7 8 9 10 IRREGULARITIES 1 4 1 4 3 2 3 5 6 4 a. Determine the c¯c¯ , Sp, UCL and LCL for a c -chart with z= 2. (Leave no...
Edit question The results of inspection of samples of a product taken over the past 5...
Edit question The results of inspection of samples of a product taken over the past 5 days are given below. Sample size for each day has been 100: Day        1             2             3             4             5 Defectives           2             6             14           3             7 Determine the UCL for this chart Determine the LCL for this chart Is this process in control?
Twenty-five samples of 100 items each were inspected when a process was considered to be operating...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating satisfactorily. In the 25 samples, a total of 185 items were found to be defective. (a) What is an estimate of the proportion defective when the process is in control? (b) What is the standard error of the proportion if samples of size 100 will be used for statistical process control? (Round your answer to four decimal places.) (c) Compute the upper and lower...
19,Suppose that you monitor the fraction defectives in ounces of a process that fills beer cans....
19,Suppose that you monitor the fraction defectives in ounces of a process that fills beer cans. The data given below were collected in the production process. Each day, 20 cans are inspected. What control chart would be the best for process monitoring? Calculate UCL and LCL of the relevant chart. Days     # of defectives 1   2 2   3 3       5 4       1 5   2 x-bar chart, UCL = 0.042 and LCL = 0 c chart, UCL = 0.1462...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating...
Twenty-five samples of 100 items each were inspected when a process was considered to be operating satisfactorily. In the 25 samples, a total of 180 items were found to be defective. (a)What is an estimate of the proportion defective when the process is in control? _________________. (b)What is the standard error of the proportion if samples of size 100 will be used for statistical process control? (Round your answer to four decimal places.) ________________. (c)Compute the upper and lower control...