Question

Insert the correct predecessor function using Microsoft Project for the following question: "Work may not start...

Insert the correct predecessor function using Microsoft Project for the following question:

"Work may not start on basement until work on foundation is 50% complete. Work on basement may not proceed past 70% until work on foundation is 100% complete."

Homework Answers

Answer #1

After lot of search, finally you zero in on an under-construction apartment to buy. Your decisions are based on cost, location, developed, accessibility, quality, reputation of builder etc. The builder as usual promises moon to every buyer and buyer gets impressed by glossy brochures and sugary words of so called sales managers. So you start dreaming about living in your own dwelling.

The builder then sets the terms for payment – 20% advance, 70% for slabs (for a typical G+3 Apartment), 10% after sale deed registration. After paying the advance (20%), you will apply for a bank loan. If your Credit

The builder will not let you modify any contents of terms and conditions of either Sale Agreement or Construction Agreement (or Agreement to build). Builder will also not entertain any questions, clarifications, doubts etc to be answered or raised. You will be left with no option but to buy it or look for a different flat. Since you would have already tried and tired of finalising/searching a flat, you will not fight with the builder – you will agree to everything.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
Question 03. Using the information in the table below, assuming that the project team will work...
Question 03. Using the information in the table below, assuming that the project team will work a standard working week (5 working days in a week) and that all tasks will start as soon as possible: Task Description Duration (Working days) Predecessor/s A Requirement Analysis 5 B Systems Design 15 A C Programming 25 B D telecoms 15 B E Hardware installation 30 B F Integration 10 C, D G System Testing 10 E, F H Training/Support 5 G I...
Question #15. Write a function file that determines the following sum using a for loop: y=i=1n(3-2i)2...
Question #15. Write a function file that determines the following sum using a for loop: y=i=1n(3-2i)2 Use n as input and test the function for n=100. Question #15. Write a function file that determines the following sum using a for loop: y=i=1n(3-2i)2 Use n as input and test the function for n=100.
Please do it by type not pics. You're at home, before you start your internship, your...
Please do it by type not pics. You're at home, before you start your internship, your local city council heard you have experience in project management. They want to create a botanical garden in your city park and have asked you to create a PERT chart of the following tasks from their Work Breakdown Structure. Code Activity Time (in hours) Immediate Predecessor(s) A Planning 20 None B Purchasing 60 Planning C Excavation 100 Planning D Sawing 30 Purchasing E Placement...
You're at home after the Spring Semester and before you start your internship, your local city...
You're at home after the Spring Semester and before you start your internship, your local city council heard you have experience in project management. They want to create a botanical garden in your city park and have asked you to create a PERT chart of the following tasks from their Work Breakdown Structure. Code Activity Time (in hours) Immediate Predecessor(s) A Planning 20 none B Purchasing 60 planning C Excavation 100 planning D Sawing 30 purchasing E Placement 20 sawing,...
Please show all work to get to the following correct answer to this question. The answer...
Please show all work to get to the following correct answer to this question. The answer is listed at the end of the question. Natural gas composed of 60. mol% methane, 30. mol% ethane, and 10. mol% propane at 25 °C and 500. psia is fed at a rate of 50. m3/hr into a boiler. In the boiler it is blended with enough air to provide 20% excess oxygen and combusted. The exhaust gas is passed through several air pollution...
You work for Microsoft in their global smart phone group. You have been made project manager...
You work for Microsoft in their global smart phone group. You have been made project manager for the design of a new smart phone. Your supervisors have already scoped the project so you have a list showing the work breakdown structure and this includes major project activities. You must plan the project schedule and calculate project duration. Your boss wants the schedule on his desk tomorrow morning!      You have been given the information in Exhibit 5.13. It includes all the...
Determine which of the following statement below are correct. Multiple statements may be correct. If you...
Determine which of the following statement below are correct. Multiple statements may be correct. If you are asked to evaluate an approximate variable, you should consider a 10% tolerance for the variable (plus or minus 10%). A firm's production function is equal to Q = K^(1/2) L^(1/2) and the Marginal Product of Labor is equal to: MP(L) = 1/2 * K^(1/2) * L^(-1/2) You know that capital (K) is currently fixed at 100 units. When labor increases from 49 to...
QUESTION 30 In Jean's work group, project decisions are made by concensus. She often does not...
QUESTION 30 In Jean's work group, project decisions are made by concensus. She often does not agree with her coworkers and refuses to agree to project ideas. Jean would be classified as a(n)   dominator. blocker. gatekeeper. opinion giver. QUESTION 32 Per Dan Ariely, all people care about is money, and the moment we give them money, we can direct them to work one way or another. This is why we give bonuses to bankers and pay in all kinds of...
Please answer the following problems using COMPLETE and GRAMMATICALLY CORRECT sentences. Please provide all supporting work...
Please answer the following problems using COMPLETE and GRAMMATICALLY CORRECT sentences. Please provide all supporting work for your solution.. 1. Show that f ( x ) = a x grows faster than g ( x ) = b x as x ⟶ ∞ if 1 < b < a. 2. Show that f ( x ) = x x grows faster than g ( x ) = b x as x ⟶ ∞ if b > 1. 3. Prove that...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT