Question

n the first phase of her project, Jan used a variety of methods to identify project...

n the first phase of her project, Jan used a variety of methods to identify project stakeholders. Next, she gave the stakeholders her project plan with accompanying Gantt charts. Finally, she set up a standardized progress reporting system to communicate with stakeholders during both the planning and execution phases. What could she have done differently to improve stakeholder involvement and communication? A) Avoid Gantt charts in stakeholder communication. B) Keep reporting schedules loose and provide information to stakeholders on an "as needed" basis. C) Have stakeholders define their objectives for the project at the outset. D) Ensure the project plan is able to accommodate all of the stakeholders' goals and requests.

Homework Answers

Answer #1

The answer is given below:

D) Ensure the project plan is able to accommodate all of the stakeholders' goals and requests.

Important stakeholders in the project would be the management of the organization, the first line managers, and team members, members from other department and sometimes outside consultant and clients too. All these stakeholders have to work hand in hand for a successful project. So Jan should involve and improve stakeholder communication by making them understand the goals.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Project Integration Management Questions Only A team member notifies you, after the fact, that she has...
Project Integration Management Questions Only A team member notifies you, after the fact, that she has added extra functionality to the project. There was no impact on the cost or schedule. What should be done as a result of this change? Make sure marketing is aware of the change. Implement change control processes to track the change. Inform the customer. Understand what functionality was added. You are having difficulty getting a project underway. You have not been able to get...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
1) Which of the following is not a valid way that a CRM system can collect...
1) Which of the following is not a valid way that a CRM system can collect information? A. accounting system B. order fulfillment system C. inventory system D. customer’s personal computer 2)Which of the following is a common marketing CRM metric? A. number of new prospective customers B. average number of service calls per day C. average time to resolution D. cost per interaction by marketing campaign 3)Which question below represents a CRM reporting technology example? A. Why did sales...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...