Individual CPM Assignment SCENARIO:

Big Organization, inc. wants to automate their warehouse and put you in charge of the project.

You already put together your team and had several productive meetings with them. Among accomplishments, you created a WBS which identified activities to be done.

Starting with the WBS and with input from your team you then identified each activity’s predecessor activities. Later, in a subsequent meeting with your team you estimated activity completion times for each activity. The table below shows the activities you identified along with predecessor activities and the estimated time each activity is expected to take. Estimated activity times are shown in the last column.

Automated Warehouse

Activity

Description

Preceding Activity

Activity Times

A

Define Requirements

none

10 days

B

Assign Team

A

5 days

C

Design Hardware

A

25 days

D

Code Software

B

20 days

E

Build & Test Hardware

C

50 days

F

Develop Patent Request

C

15 days

G

Test Software

D

35 days

H

Integrate Systems

E, F, G

15 days

B. Second tab (Worksheet) in Microsoft Excel template Workbook: Calculate the EST, EFT, LST, LFT, and slack for each activity. Also determine the total project completion time and the critical path(s). Note that some calculations have been done for you (15 points). Example table:

Expected

Critical?

Activity

Pred

Time

EST

EFT

LST

LFT

Slack

Y/N

A

-

10

B

A

5

C

A

25

D

B

20

E

C

50

F

C

15

G

D

35

H

E,F,G

15

Critical Path =

Project Length =

days

Homework Answers

Answer #1

Formula

Critical path = A-C-E-H

Project duration = 100 days

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of...
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times: Immediate Activity Predecessor Time A — 3 B — 4 C — 2 D A, B, C 2 E A, D 8 F C, D 7 G D, E 5 H F...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A...
Use the following data for problems 34, 35, and 36 Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY...
Problem 5-7 The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 b. What is the critical path? A-C-D-F-G A-C-D-E-G A-B-E-G A-B-D-F-G c. How many weeks will it take to complete the project? Number of weeks             d. How much slack does activity B have? Slack of activity B             week(s)
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR...
The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) A — 7 B A 6 C A 2 D C 4 E B D 3 F D 4 G E F 6 a. Draw the network b. What is the critical path c. How many weeks will it take to complete the project d. Identify the early start, early finish, late start, and late finish for each activity in the project...
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion)...
A project is represented by the activity durations (in days, estimated at 90% likelihood of completion) and precedence requirements shown in the table. How many project buffers are needed if this project is managed using critical chain methodology? Activity Predecessor Length Activity Predecessor Length A -- 18 E C, D 13 B -- 16 F C 9 C A 22 G E, F 15 D B 14 ​ ​ ​ options: 0 1 2 3
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A...
Activity Completion (Days) Immediate Precedence A. Architectural Design 3 - B. Clearing of Land 6 A C. Fencing of project site 7 A D. Digging of foundation 5 A E. Completion of foundation work 13 B,C F. Raising of pillars and block work. 8 C,D G. Roofing 11 D,F H. Furnishing of the cathedral 6 G,E a. Redraw the network diagram for the construction of the National Cathedral by using the above information provided in the table to complete the...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days)...
Given the following information for a project, answer the following questions: Activity Predecessor Activity Time (days) A - 6 B - 8 C A, B 5 D B 4 E C 7 F C, D 3 G D 6 H E, F, G 5 Fill in the following table. Activity ES EF LS LF Slack CP A 0 No B Yes C Yes D No E Yes F No G 18 14 20 No H 25 20 25 Yes Draw...
The project of an interior design upgrade at one of the Citibank branches consists of six...
The project of an interior design upgrade at one of the Citibank branches consists of six activities. The tasks, durations (in days), and predecessor relationships are as follow: Activity Immediate Predecessors Activity Time A - 3 B A 4 C A 5 D B, C 4 E C 3 F D, E 3 Calculate the slack times and identify the critical path(s).
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ___ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
Given is a CPM project network diagram as shown below. Activity Start A B C D...
Given is a CPM project network diagram as shown below. Activity Start A B C D E F G H End days 0 2 6 8 3 4 2 3 2 0 a) The Project Completion time = ____ days. b) The Earliest Start time, ES, of Activity G = ____ days. c) The Latest Finish time, LF, of Acitivity C = ____ days. d) The critical activities are = ____ (ex. Fill in answer as: ABCD)
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT