rick wing has a repetitive manufacturing plant producing automobile steering wheels, use the following date to prepare for a reduse lots size , the firm uses a work year of 295 days ;
Setup labor cost per hour = $ 40
Annual Holding cost per unit year = $ 15
Daily production ( 8 hours) = 960 units / day
Annual Demand = 35,400 (295 days each * daily demand of 120)
Desired lot size (2 hour or production) = 240 units
find;
a/ setup cost ? b/ setup time?
Annual demand(D) = 35400 units
Daily demand(d) = 120 units
Daily production(p) = 960 units
Annual Holding cost(H) = $15 per unit
Desired lot size(Q) = 240 units
Set up labor cost per hour = $40
a) Set up cost(S) = [ Square of Q X H X (1-d/p) ] / 2D
= [ Square of 240 X 15 X (1-120/960) ] / (2 X 35400)
= (57600 X 15 X 0.875) / 70800
= 756000 / 70800
= $10.68
b) Set up time = Set up cost / setup labor cost per hour
= $10.68 / $40
= 0.0267 hour
= (0.082 X 60) minutes
= 4.92 minutes