Question

Question 1. AUMexx manufactures tables in its production plant. The plant takes custom orders from clients....

Question 1. AUMexx manufactures tables in its production plant. The plant takes custom orders from clients. Each order is processed in three stations. First, information about the order is passed to Station A where an employee spends 1.5 hours at Station A to create the legs for the custom table. The information about the order and table legs are then transferred to Station B where an employee takes 2.5 hours to create a table top. The order information, legs, and top are then transferred to Station C where an employee takes 1 hour to assemble the table. Each station has one employee devoted to the assigned task.

Part-I: Use the information above to answer the questions a to c.

(1.5 points) Which station is the bottleneck?

(0.5 point) What is the hourly production capacity of the process (measured in number of orders completed per hour)?

(1 point) Suppose 1 order arrives every 3 hours. Can this facility start processing incoming orders without any delays? Explain why or why not. Does your answer change if the number of arrivals is subject to variability and 1 order arrives every 3 hours on the average? Explain clearly why or why not.

Part-II: Unexpected events at AUMexx influence the production times and the demand. Use the information below to answer questions d and e.

(2 points) It takes AUMexx an average of 5 days to complete an order. The process is in steady state, i.e., it works at a stable rate. At any time, not all pieces associated with an order have been manufactured and assembled. There are some intermediate products (such as table legs, table tops, half assembled tables) in the plant. These are considered work-in-process inventory (WIP). The average WIP is estimated to be 80 orders at any given time. That is, 80 orders are at various stages of manufacturing. What is the number of orders completed by AUMexx in a day?

(3 points) Of the 80 orders that constitute the WIP in the plant, 17 are at station A, 41 are at station B and 22 are at station C. How long (in days) does an order spend at each of the stations:

i. at station A?

ii. at station B?

iii. at station C?

Homework Answers

Answer #1

1)

Station A time = 1.5 hours

Station B time = 2.5 hours

Station C time = 1 hour

a) Station B is bottleneck due to highest time

b) Hourly production capacity = Capacity of bottleneck process = 1/2.5 orders per hour = 0.4 orders per hour

c) Yes, the facility can start processing orders without delay in case order comes in every 3 hours as the bottleneck process time is less than incoming order frequency.

In case there is variability in arrival, then there might be delay if two orders come with little gap between them. Example: If gap between order is 1 hour only, then, it will have to wait in station A and B.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton,...
Chairvana’s Table Assembly Operations: Chairvana Inc. manufactures metal tables and chairs at its plant in Paxton, Illinois. Recently hired general manager, Bob Behar, is concerned about the large inventories and manufacturing inefficiencies in the plant. The Paxton plant has two separate assembly lines – one for chairs and one for tables. Demand for chairs is significantly larger than tables, so Bob decides to tackle the table assembly process for first. Bob has recently hired a summer intern, Eileen Mayer, who...
Process Costing Problem Stein Industries manufactures outdoor chairs in its Plant #2. Stein began July with...
Process Costing Problem Stein Industries manufactures outdoor chairs in its Plant #2. Stein began July with 500 units in Beginning Work in Process. A total of 18,000 units were started into production. Ending WIP was 500 units that were 80% complete. July Cost Data: Work in Process July 1              $15000 Materials      288,000 Labor       133900 Manufacturing Overhead         96,700   Total $533,600 Units Table Whole Units Beginning WIP Units Started Units to Acct For Equivalent Units Units Transferred Ending...
Required information Upriver Parts manufactures two products, V-1 and V-2, at its River Plant. Selected data...
Required information Upriver Parts manufactures two products, V-1 and V-2, at its River Plant. Selected data for an average month for the two products follow. V-1 V-2 Units produced 10,000 1,000 Direct materials cost per unit $ 2 $ 4 Machine hours per unit 1 2 Production runs per month 80 40 Production at the plant is automated and any labor cost is included in overhead. Data on manufacturing overhead at the plant follow. Machine depreciation $ 72,000 Setup labor...
QUESTION 1 Which of the following best exemplifies offshoring? A. A U.S. company employs foreign nationals...
QUESTION 1 Which of the following best exemplifies offshoring? A. A U.S. company employs foreign nationals at its U.S. based headquarters. B. A U.S. company translates novels originally written in foreign languages into English for distribution in the U.S. market. C. A U.S. company starts a chain of fusion restaurants to cater to the American public’s evolving palates. D. A U.S. company purchases footwear made in Europe to distribute to retailers in the United States. E. A U.S. company that...
15. Ravsten Company uses a job-order costing system. On January 1, the beginning of the current...
15. Ravsten Company uses a job-order costing system. On January 1, the beginning of the current year, the company’s inventory balances were as follows:      Raw materials $ 20,000   Work in process $ 11,600   Finished goods $ 30,800 The company applies overhead cost to jobs on the basis of machine-hours. For the current year, the company estimated that it would work 36,800 machine-hours and incur $171,120 in manufacturing overhead cost. The following transactions were recorded for the year: Raw materials...
Fancy Millwork has a factory that produces custom kitchen cabinets. It has multiple product lines. Materials...
Fancy Millwork has a factory that produces custom kitchen cabinets. It has multiple product lines. Materials and labor for the cabinets are determined by each job. To simplify the assignment, we will assume the following average costs. The company estimates that it will have 32,000 direct labor hours in total for the kitchen cabinets. The materials include $2,000 for the wood and other materials on a per job basis. It requires 40 hours of labor on average for a custom...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft in the global market. The other major producer is European Airbus. Boeing produces three models in Everett, Washington: 747s, 767s, and 777s. The planes are all produced in the same building. At any one time, there may be as many as six planes in various stages of production. Obviously the building has to be fairly large to accommodate such a huge undertaking. In fact,...
This case assignment draws from the Business Information Systems and the Systems Acquisition and Development modules...
This case assignment draws from the Business Information Systems and the Systems Acquisition and Development modules (Chapters 5 to 8). Its purpose is to provide you with experience in analyzing organizational information systems, making recommendations to improve these systems, and formulating a plan to execute on your recommendations. 1. Recommend one of your alternatives that is the best solution to the main issue and justify your recommendation. Your justification should be based on the key decision criteria and you must...
QUESTION 1 Match the correct answer to the question. Each option may be used more than...
QUESTION 1 Match the correct answer to the question. Each option may be used more than once.    When would Cost of Goods Sold be debited?    When would Manufacturing Overhead be debited? When would Finished Goods be debited?    When would Manufacturing Overhead be credited? When would Finished Goods be credited? A. to record actual indirect labor, actual indirect materials, rent or accumulated depreciation on the plant, actual utility expense incurred. B. when goods are finished. C. when good...
Orange County Chrome Company manufactures three chrome-plated products—automobile bumpers, valve covers, and wheels. These products are...
Orange County Chrome Company manufactures three chrome-plated products—automobile bumpers, valve covers, and wheels. These products are manufactured in two production departments (Stamping and Plating). The factory overhead for Orange County Chrome is $213,389. The three products consume both machine hours and direct labor hours in the two production departments as follows: Direct Labor Hours Machine Hours Stamping Department Automobile bumpers 558 803 Valve covers 295 557 Wheels 340 597 1,193 1,957 Plating Department Automobile bumpers 171 1,166 Valve covers 175...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT