What does Project Cost Control NOT include?
Ensuring that cost expenditures exceed the authorized funding |
Ensuring all change requests are acted on in a timely manner |
Monitoring work performance against funds expended |
Managing actual changes as and when they occur |
The correct answer is "Ensuring that cost expenditures exceed the authorized funding".
Project cost control is nothing but the process by which the status of the project is monitored so that the project costs are updated and changes to the cost baseline are managed. Project cost control include: -