Question

Activities Predecessors Duration(weeks) Labour A 4 5 B A 3 5 C B 2 5 D...

Activities Predecessors Duration(weeks) Labour
A 4 5
B A 3 5
C B 2 5
D C 1 5
E B 2 5
F E 8 5
G D 10 5
H B 2 5
I B 3 5
J F,G,I 3 5
K H 2 5
L J,K 3 5
M L 1 5

i.Construct an activity on the arrow network

ii. Determine the Duration of the Critical Path;

iii. Draw the corresponding Gantt chart

iv. Draw the resource allocation chart.

Homework Answers

Answer #1

PLEASE RATE POSITIVE IF THOU LIKE MY ANSWER TO PROTECT MY EMPLOYMENT

i) Activity on arrow network

II)

PATH PATH LENGTH
ABCDGJLM 4+3+2+1+10+3+3+1 = 27
ABEFJLM 4+3+2+8+3+3+1 = 24
ABIJLM 4+3+3+3+3+1 = 17
ABHKLM 4+3+2+2+3+1 = 15

The critical path is path with longest length . Hence critical path is ABCDGJLM

iii) Gantt chart

iv) resource allocation chart

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3...
Activity Duration (days) Predecessors Resources A 5 - Jane B 7 A Marry, Kate C 3 A Dennis D 3 B Kate E 8 D William F 10 C Sam G 8 F William H 3 E, G Jane 1. Draw the network diagram and indicate the critical path. 2. Draw the network diagram by specifying Early Start, Early Finish, Late Start, Late Finish, and slacks. 3. Indicate all the activities, duration, start and finish dates, predecessors, resources in a...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4...
Activity A Duration 6 Predecessor - Crash weeks - Crashing cost per week - B 4 A 2 $480 C 5 A 1 $380 D 6 A 3 $450 E 5 B 2 $430 F 4 B,C 3 $350 G 5 C,D 2 $410 H 6 D 2 $570 I 5 E,F 2 $540 J 6 E,F,G 2 $530 K 3 G,H 1 $550 L 4 I,J 1 $560 M 5 I,J,K - $620 N 6 H,K,J 1 $650 O...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including...
QUESTION 2. The following table explain the logical relationship of activities of a given project, including the duration in weeks of each activity. Activity Follows Duration (Weeks) M G, F 4 F Start 6 G Start 3 D Start 7 K D, G 5 L K, J 8 J D 3 S L, M, F 4 Finish S Draw the network Perform the forward path as determine the project duration (5 Marks) Perform the back path and determine the critical...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and...
Draw the Activity-on-Arrow (AoA) and Activity-on-Node (AoN) networks using the activity dependency table given below and find the critical path(s) Activities Predecessor duration A - 2 B - 10 C A 9 D A,B 7 E A,B 9 F B 5 G C 10 H D,E 1 I D,E,F 2 J F 7 K C,H,I 2 L I,J 2 M I 1 N G,K 5
Assuming that the cost of each activity is linearly distributed over its duration, create two budgets...
Assuming that the cost of each activity is linearly distributed over its duration, create two budgets as follows: The first budget should assume an early-start schedule The second budget should assume a late-start schedule Explain why the two budgets are different Activity Duration (days) Immediate predecessors Cost A 3 – $3,000 B 4 –  2,000 C 3 –  6,000 D 2 C  2,000 E 1 B  1,000 F 5 A 10,000 G 2 B  4,000 H 3 B  9,000 I...
AON The table given below contains the activity label, its respective duration (in weeks) and its...
AON The table given below contains the activity label, its respective duration (in weeks) and its precedents. Use critical path method to find the critical path and activities of this project. ACTIVITY DURATION (IN WEEKS) PRECEDENTS A 6 – B 4 – C 3 A D 4 B E 3 B F 10 – G 3 E, F H 2 C, D
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
Given below are the durations of and the precedence relationships among the activities required to compute...
Given below are the durations of and the precedence relationships among the activities required to compute a project. 1) construct an AOA network of the project 2)what is the critical path? determine the expected duration of the project. 3)compute the standard deviation of the critical path Duration(days) Activity pre-decessor(s) a m b A - 4 7 12 B A 6 9 13 C A 5 7 9 D B,C 3 5 8 E B 7 8 10 F A 2...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate...
1. A landscaping upgrade project consists of following activities. Times are given in weeks. Activity Immediate Predecessor Activity Time A - 5 B A 8 C A 7 D - 6 E B, D, C 8 F D 3 G D 3 a. Draw the network diagram and find the ES, EF, LS, LF, and slack for each activity. b. Construct an early-start-date Gantt chart for the project. c. As a project manager, where would you focus your attention, given...
Consider a project having the following six activities:                                  
Consider a project having the following six activities:                                                      Immediate                                                  Max        Crash cost             Activity                           Predecessors           Time (weeks)             Crash*    per week                   A                                none                                    6                          6                N/A                   B                                none                                    5                          2               $500                   C                                A                                       3                          2             $1000                   D                                A, B                                    4                          2             $2000                   E                                 C, D                                    5                          2             $1250                   F                                D                                       6                          2             $1000                                                                                                 *Shortest possible time for the task Draw the project network and list the...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT