Activities | Predecessors | Duration(weeks) | Labour |
A | 4 | 5 | |
B | A | 3 | 5 |
C | B | 2 | 5 |
D | C | 1 | 5 |
E | B | 2 | 5 |
F | E | 8 | 5 |
G | D | 10 | 5 |
H | B | 2 | 5 |
I | B | 3 | 5 |
J | F,G,I | 3 | 5 |
K | H | 2 | 5 |
L | J,K | 3 | 5 |
M | L | 1 | 5 |
i.Construct an activity on the arrow network
ii. Determine the Duration of the Critical Path;
iii. Draw the corresponding Gantt chart
iv. Draw the resource allocation chart.
PLEASE RATE POSITIVE IF THOU LIKE MY ANSWER TO PROTECT MY EMPLOYMENT
i) Activity on arrow network
II)
PATH | PATH LENGTH | |
ABCDGJLM | 4+3+2+1+10+3+3+1 = | 27 |
ABEFJLM | 4+3+2+8+3+3+1 = | 24 |
ABIJLM | 4+3+3+3+3+1 = | 17 |
ABHKLM | 4+3+2+2+3+1 = | 15 |
The critical path is path with longest length . Hence critical path is ABCDGJLM
iii) Gantt chart
iv) resource allocation chart