Question

Based on the 10 Operation Decisions Table, we would begin with the product and end with...

Based on the 10 Operation Decisions Table, we would begin with the product and end with layout and location.

True

False

Gantt charts are low-cost means of helping managers make sure that 1. activities are planned, 2. order of performance is documented, 3. activity time estimates are recorded, and 4. overall project time is developed. Gantt charts, thought, do not illustrate the interrelationships between the activities and the resources.

True

False

Optimistic time, Pessimistic time and Most likely time are the worst completion time activities that could be obtained in a PERT network.

True

False

In PERT, we employ a probability distribution based on three time estimates for each activity, such as Optimistic time, Pessimistic time and Most likely time.

True

False

Homework Answers

Answer #1

False that Based on the 10 Operation Decisions Table, we would begin with the product and end with layout and location.

True that Gantt charts are low-cost means of helping managers make sure that 1. activities are planned, 2. order of performance is documented, 3. activity time estimates are recorded, and 4. overall project time is developed. Gantt charts, though, do not illustrate the interrelationships between the activities and the resources.

False. Because optimistic time is the best activity completion time that could be obtained in a PERT network.

True that In PERT, we employ a probability distribution based on three time estimates for each activity, such as Optimistic time, Pessimistic time and Most likely time.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A landscaping project consists of the activities below. The following information describes the relationships between the...
A landscaping project consists of the activities below. The following information describes the relationships between the activities that need to be completed for this project.                         Immediate Activity      Predecessors                A      -                B      A                C      A                D      C                E       B, D Using the data above, develop a network for this project. The following are estimates of optimistic, most likely, and pessimistic times. Activity      Optimistic time Most Likely Time Pessimistic Time                A      3                                   4                                  ...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of...
(a). State TWO contrasts between Pure Project Teams and Matrix Project Teams. Give an example of each. 3(b). The following data relates to the activities required for a project. Since exact duration for each activity is not known for certain, three time estimates were made, namely: - the optimistic, most likely and pessimistic time estimates. The precedence relationships are also shown in the data below. You will need to analyze this problem using what you learned in Chapter 18 of...
Project Management Scenario: You are a consultant with expertise in project management strategies. Select a possible...
Project Management Scenario: You are a consultant with expertise in project management strategies. Select a possible project management situation from your current or future professional experience. As a project management consultant, you are tasked with developing a project management plan for this project. Your goal is to maximize the time, resources and finances associated with the project in the best interests of the business/company. You will need to write a professional memo to the business/company owner describing the management of...
A partially solved PERT problem is detailed in the table below. Times are given in weeks....
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Immediate Predecessor(s) Optimistic Most Likely Pessimistic A -- 8 10 15 B -- 7 8 9 C A 5 6 10 D A 3 3 3 E B,D 1 5 9 F B,D 4 7 10 G C 3 8 10 H E 5 7 9 I E 4 5 8 J F 2 5 8 K H, I 1 3 6 a)...
I need to answer the questions based on the following article The article is Although the...
I need to answer the questions based on the following article The article is Although the virus has delayed the budget until October, Treasurer Josh Frydenberg will deliver an update on the budget and – more importantly – the economy, within the next fortnight. But last week the secretary to the Treasury dropped some big hints on what to expect. In evidence to the Senate committee inquiring into the response to the virus, Dr Steven Kennedy started with the outlook...
During the trial, lawyers for the accused said that the men believed that the accounting decisions...
During the trial, lawyers for the accused said that the men believed that the accounting decisions they made were appropriate at the time, and that the accounting treatment was approved by Nortel’s auditors from Deloitte & Touche. Judge Marrocco accepted these arguments. Marrocco added he was “not satisfied beyond a reasonable doubt” that the trio (i.e., Dunn, Beatty, and Gollogly) had “deliberately misrepresented” financial results. Given the facts of the case, do you believe Judge Marrocco’s decision was justified? Explain....
The Business Case for Agility “The battle is not always to the strongest, nor the race...
The Business Case for Agility “The battle is not always to the strongest, nor the race to the swiftest, but that’s the way to bet ’em!”  —C. Morgan Cofer In This Chapter This chapter discusses the business case for Agility, presenting six benefits for teams and the enterprise. It also describes a financial model that shows why incremental development works. Takeaways Agility is not just about the team. There are product-management, project-management, and technical issues beyond the team’s control. Lean-Agile provides...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary...
Please answer the following Case analysis questions 1-How is New Balance performing compared to its primary rivals? How will the acquisition of Reebok by Adidas impact the structure of the athletic shoe industry? Is this likely to be favorable or unfavorable for New Balance? 2- What issues does New Balance management need to address? 3-What recommendations would you make to New Balance Management? What does New Balance need to do to continue to be successful? Should management continue to invest...
What tools could AA leaders have used to increase their awareness of internal and external issues?...
What tools could AA leaders have used to increase their awareness of internal and external issues? ???ALASKA AIRLINES: NAVIGATING CHANGE In the autumn of 2007, Alaska Airlines executives adjourned at the end of a long and stressful day in the midst of a multi-day strategic planning session. Most headed outside to relax, unwind and enjoy a bonfire on the shore of Semiahmoo Spit, outside the meeting venue in Blaine, a seaport town in northwest Washington state. Meanwhile, several members of...
What role could the governance of ethics have played if it had been in existence in...
What role could the governance of ethics have played if it had been in existence in the organization? Assess the leadership of Enron from an ethical perspective. THE FALL OF ENRON: A STAKEHOLDER FAILURE Once upon a time, there was a gleaming headquarters office tower in Houston, with a giant tilted "£"' in front, slowly revolving in the Texas sun. The Enron Corporation, which once ranked among the top Fortune 500 companies, collapsed in 2001 under a mountain of debt...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT