Question

PERT and CPM both follow the same steps. True False An activity that finds all the...

PERT and CPM both follow the same steps.

True

False

An activity that finds all the late start and late finish time and starts with the first node is known as the backward pass.

True

False

Another term for slack time is free float.

True

False

Under AOA , circles represent activities.

True

False

Multi domestic strategy- is a strategy in which operating decisions are centralized to each country to enhance local responsiveness. A company like Heinz accommodates global taste because local taste is not critial.

True

False

Homework Answers

Answer #1

True. PERT and CPM both follow the same steps, which are six steps.

False. Backward pass is an activity that finds all the late start and late finish time, but it doesn’t start with first node.

False. Free float is another term for free slack and not for slack time.

False. Under AOA, activities are represented by Arrow.

False. Multi-domestic is a strategy in which operating decisions are decentralized to each country to enhance local responsiveness.

False. A company like Heinz accommodates local tastes because global integration of the production process is not critical.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT