Question

The S&OP team at Kansas Furniture, has received the following estimates of demand requirements: July Aug....

The S&OP team at Kansas Furniture, has received the following estimates of demand requirements:

July

Aug.

Sept.

Oct.

Nov.

Dec.

1,800

1,200

1,400

1,800

1,000

1,600

Assume regular-time production cost of $50 per unit, inventory carrying costs of $25 per unit per month, and 100 unit beginning inventory at the beginning of July. Create an aggregate plan that would produce at a steady rate of 1,300 units per month and subcontract additional units at a $60 per unit premium cost. What is the cost of this plan?

Demand

Beginning

    Inventory    

Regular

Time

Production

Subcontract

Ending

Inventory

July

1800

Aug.

1200

Sept.

1400

Oct.

1800

Nov.

1000

Dec.

1600

Total

Regular Time Production Cost =                                                                        

Subcontract Cost =                                                                      

Inventory Cost =                                                                                

Total Cost =    

Homework Answers

Answer #1
Demand Beginning inventory Regular time production Subcontract Ending inventory
July 1800 100 1300 400 0
Aug 1200 0 1300 0 100
Sept 1400 100 1300 0 0
Oct 1800 0 1300 500 0
Nov 1000 0 1300 300
Dec 1600 300 1300 300 0
Units 7800 1200 400
Cost 50 60 25 Total cost
390000 72000 10000 472000

Regular Time Production Cost = $390000   

Subcontract Cost = $72000   

Inventory Cost = $10000

Total Cost = $472000

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$30 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1,000 units per month and subcontract additional units at a ?$65 per unit premium cost. Subcontracting...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the...
The? S&OP team at Kansas? Furniture, has received estimates of demand requirements as shown in the table. Assuming? one-time stockout costs for lost sales of ?$125 per? unit, inventory carrying costs of ?$20 per unit per? month, and zero beginning and ending? inventory, evaluate these two plans on an incremental cost? basis: Plan? A: Produce at a steady rate? (equal to minimum? requirements) of 1 comma 000 units per month and subcontract additional units at a ?$70 per unit premium...
Flag Bike components manufactures bicycle wheels and had just received their forecasts for the next 6...
Flag Bike components manufactures bicycle wheels and had just received their forecasts for the next 6 months. Currently, flag bike employs 15 full time, highly skilled employees, each of whom can produce 100 wheels per month. There are 300 wheels in beginning inventory and at present, flag bikes’s customers will tolerate backorders of up to 200 units per month. The associated costs are $4 per unit for regular time and 7.50 per unit for overtime. Inventory holding costs are $3...
Neal Industries manufactures blue jeans for the teen market. The S&OP team has agreed upon a...
Neal Industries manufactures blue jeans for the teen market. The S&OP team has agreed upon a demand forecast for the following year, as shown below. The company begins with 1,800,000 jeans in safety stock and desires to maintain this level consistently (and end with this level), assume that the overtime production wage rate is $24 per hour. Quarter Demand 1 7,500,000 2 8,300,000 3 15,000,000 4 12,500,000 Current workforce 300 workers Average output per worker 25,000 jeans per quarter Inventory...
Jerusalem Medical? Ltd., an Israeli producer of portable kidney dialysis units and other medical? products, develops...
Jerusalem Medical? Ltd., an Israeli producer of portable kidney dialysis units and other medical? products, develops a? 4-month aggregate plan. Demand and capacity? (in units) are forecast as? follows: ????????????????????????????????????????????????????????????????????????????????????????????????????????????????   Capacity Source Month 1 Month 2 Month 3 Month 4 Labor ??????Regular time 225 275 300 300 ??????Overtime 15 24 26 24 Subcontract 14 15 13 15 Demand 240 314 331 301 The cost of producing each dialysis unit is ?$875 on regular? time, ?$1,310 on? overtime, and ?$1,600 on...
Wormwood, LTD produces a variety of furniture products. The planning committee wants to produce an aggregate...
Wormwood, LTD produces a variety of furniture products. The planning committee wants to produce an aggregate plan for the next 6 months. Complete the spreadsheet cells colored in blue. Month 1 2 3 4 5 6 Demand 160 150 160 180 170 140 Demand Units Capacity Cost Per Unit Regular 150 150 150 150 160 160 Regular Units $50 Max Overtime 10 10 10 10 10 Overtime Units $75 Max Subcontract 10 10 10 10 10 10 Subcontract Units $80...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate...
Suppose that demand data for widgets made by XYZ Inc. is given below. Using an appropriate method (level , chase or mixed), plan the production (i.e. specify the production quantities and complete the table below) such that the total cost is made as small as possible. Regular time production capacity is 7000 units per month. They can also produce in overtime up to 5000 units per month. There is no other method of production and the cost of regular time...
Mate Boomerang Corporation manufactures and sells plastic boomerangs. Expected boomerang sales (in units) for the upcoming...
Mate Boomerang Corporation manufactures and sells plastic boomerangs. Expected boomerang sales (in units) for the upcoming months are as follows: July Aug. Sept. Oct. Nov. Dec. Budgeted unit sales 12,000 15,000 10,000 8,000 7,000 11,000 Mate likes to maintain a finished goods inventory equal to 10% of the next month's estimated sales. Seven ounces of plastic resin are needed to produce every boomerang. Mate likes to have enough plastic resin on hand at the end of the month to cover...
While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging...
While the demand for regular fabric has declined, the demand for medical-grade fabric has been surging in the market. In response, the management at Fabric Mills quickly bumped up the regular output of medical-grade fabric by reassigning workers from the production of regular fabric and rehiring retired workers. Table 2 shows the demand forecast and capacity for medical-grade fabric. Note that overtime is limited to 20% of the regular capacity. The availability of subcontract is also limited due to the...
The president of Hill? Enterprises, Terri? Hill, projects the? firm's aggregate demand requirements over the next...
The president of Hill? Enterprises, Terri? Hill, projects the? firm's aggregate demand requirements over the next 8 months as? follows: January 1,500 May February 1,700 June 2,200 March 1,600 July 1,700 April 1,900 August 1,700 Her operations manager is considering a new? plan, which begins in January with 200 units of inventory on hand. Stockout cost of lost sales is ?$100per unit. Inventory holding cost is ?$20 per unit per month. Ignore any? idle-time costs. The plan is called plan...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT