Question

The following jobs have arrived in order. Job Time Due Date 1 4 15 2 7...

The following jobs have arrived in order.

Job

Time

Due Date

1

4

15

2

7

16

3

2

8

4

6

21

5

3

9

If we are interested in Job Lateness as a measure, is SPT or FCFS the better sequencing method to use?

If we are interested in Flow Time as a measure, is SPT or FCFS the better sequencing method to use?

Homework Answers

Answer #1

Job

Time

Due Date

1

4

15

2

7

16

3

2

8

4

6

21

5

3

9

Using FCFS scheduling:

Flow time for 1st job = time of that job

Flow time for 2nd job onwards = flowtime of the previous job + time of the considered job

Lateness = Flowtime – Due Date

Job

Time

Flowtime

Due Date

Lateness

1

4

4

15

-11

2

7

11

16

-5

3

2

13

8

5

4

6

19

21

-2

5

3

22

9

13

Total Flowtime = 69

Total lateness = 0

Number of tasks = 5

Average flowtime = total flowtime/number of tasks = 69/5 = 13.8

Average lateness = total lateness/number of tasks = 0/5 = 0

Using Shortest Processing Time (SPT):

Flow time for 1st job = time of that job

Flow time for 2nd job onwards = flowtime of the previous job + time of the considered job

Lateness = Flowtime – Due Date

Job

Time

Flowtime

Due Date

Lateness

3

2

2

8

-6

5

3

5

9

-4

1

4

9

15

-6

4

6

15

21

-6

2

7

22

16

6

Total Flowtime = 53

Total lateness = -16

Number of tasks = 5

Average flowtime = total flowtime/number of tasks = 53/5 = 10.6

Average lateness = total lateness/number of tasks = -16/5 = -3.2

Answers:

If we are interested in Job Lateness as a measure, is SPT or FCFS the better sequencing method to use?

As, the lateness of STP is less than the lateness of FCFS, SPT is better.

If we are interested in Flow Time as a measure, is SPT or FCFS the better sequencing method to use?

As, the flowtime of STP is less than the flowtime of FCFS, SPT is better.

********

IF YOU HAVE ANY DOUBT, KINDLY COMMENT. I WOULD LOVE TO HELP YOU!!!

IF YOU LIKE THE ANSWER, PLEASE GIVE AN UP-VOTE OR THUMB UP. THIS WILL ENCOURAGE ME TO ANSWER MORE!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job...
Today is Nov. 16. The following jobs need to be scheduled on the same machine. Job A, Process time =14 days, and due date November 26 Job B, Process time= 11 days, and due date = November 25 Job C, Process time =7 days, and due date= December 14 Job D, Process time=6 days, and due date= November 29 Job E, Process time= 2 days, and due date= November 20 Schedule the jobs according to SPT. What are the average...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs...
Part 3. Questions 3,4,5. [ Use Video-2 under Scheduling heading. ] [Note: The order of jobs in a schedule ABCDE is 1st,2nd,3rd,4th,5th, respectively.] Five jobs arrived to be processed with the processing times and due dates. Present Date= 300 Work Order A B C D E Processing Times (Days) 14 5 40 12 7 Due Date 167 163 195 191 161 . . . Question 3. The FIFO schedule is “ABCDE” (where job “A” is the first job) and the...
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table....
A Northern British Columbia lumberyard has four jobs on order, as shown in the following table. Today is day 205 on the yard’s schedule. Job Due Date Remaining Time (Days) A 212 6 B 209 3 C 214 10 D 210 8 In what sequence would the jobs be ranked according to the following decision rules: a) FCFS b) SPT c) LPT d) EDD e) Critical ratio Which is best and why? Which has the minimum lateness?
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
Five jobs are ready for processing at time zero through a workstation. The details of the...
Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table. Job Processing Time (days) Due Date A 5 11 B 6 16 C 3 19 D 4 10 E 2 9 Using the earliest due date (EDD) rule, the average lateness for the five jobs is:
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
You have the following information on four jobs. Today is the beginning of day 1, so...
You have the following information on four jobs. Today is the beginning of day 1, so you can assume that the Time needed = work remaining and Due (days) = time remaining. Job Time Needed (days) Due (days) P 8 8 Q 10 23 R 3 17 S 6 30 T 4 29 U 7 24 1. If you order these jobs by Shortest Process Time rule, the order will be: 2. If you order these jobs by Earliest Due...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center...
The following jobs are waiting to be processed at Rick? Solano's machine center.? Solano's machine center has a relatively long backlog and sets a fresh schedule every 2? weeks, which does not disturb earlier schedules. Below are the jobs to be scheduled? today, which is day 241 ?(day 241 is a work? day). Job names refer to names of clients and contract numbers. Compute all times based on initiating work on day 241. (Job) (Date Job Received) (Due Date Duration...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown...
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: Processing Due Job Time (days) Date (Days) W 4 4 X 3 5 Y 2 2 Z 1 1 If he uses the shortest processing time first (SPT) priority rule to schedule these jobs, what will be the average number of jobs in his shop today? A. 0 B. 1 C. 2 D. 3 E. 4
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs...
Part 4.   Questions 6,7. [ Use Video-1 under Scheduling heading. ] [Note: The order of jobs in a schedule is 1st,2nd,3rd,4th,5th, for A,B,C,D,E, respectively.] The jobs A,B,C,D,E, arrived in that order to be processed on two machines. Job A B C D E Time on Machine 1 45 53 63 31 75 Time on Machine 2 42 65 61 53 77 Question 6. Which is the Johnson’s Rule schedule?      (A) ‘ACEBD’     (B) ‘DCABE’     (C) ‘DBECA’     (D) ‘DABEC’   (E) none...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT