Girish Shambu and William Reisel are teammates at a discount? store; their new job is assembling bicycles for customers. Assembly of a bike has a learning rate of 80?%. They forgot to time their effort on the first? bike, but spent 6 hours on the second. They have 6 more bikes to do. Determine approximately how much time will be? (was) required? for:
c) The total amount of hours to build the 8 units? =
hours? (round your response to two decimal? places).
Given t2 = 6 hrs---- A
Learning rate = 0.8
b= Log learning rate / Log 2 = log 0.8 / log 2 = -0.322
t2= t1 (n)^b =t1(2)^(-0.322)
Putting in A:
t1(2^-0.322) = 6
0.799 t1=6
So, t1 = 6/0.799 = 7.5 hrs
Unit |
Unit Time |
Cumulative Time |
t1 |
7.5 |
7.5 |
t2 |
6 |
13.5 |
t3 |
5.265 |
18.765 |
t4 |
4.8 |
23.565 |
t5 |
4.46 |
28.025 |
t6 |
4.2 |
32.225 |
t7 |
4.005 |
36.23 |
t8 |
3.84 |
40.07 |
Total amount of hours to build 8 units = 40.07 hours