Johnny Thompson's poster company works on 3 types of printing jobs, each of which could be produced on the same model machine. The predicted annual demands and typical order sizes are shown in the table below. The company has 2000 production hours available each year and requires a 10% capacity cushion to allow for preventive maintenance, breakdowns, and other unforeseen circumstances. How many printing machines must they have under these circumstances? Show all of your work.
Job Type | Job A | Job B | Job C |
Demand | 8000 | 4000 | 5000 |
Process time per unit | .8 | .75 | .25 |
Average order size | 40 | 100 | 50 |
Setup time (hours) | 1 | .75 | .5 |
Total time required for all jobs = 6600+3030+1300 = 10930
Adding 10% capacity cushion for preventive maintainence = 10930 + 10%*10930 = 12023
Total production hours = 2000
Thus 6 machines (12023/2000) are required